FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
6 Installing Devices Inside the Pre-fab. Module
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
56
Secure the temperature probe to the position on the water refill and drainage pipe. The position is the
point where the electric heating belt is wrapped 50 cm long around the water refill and drainage pipe
from the water refill and drainage pipe port.
Figure 6-22
Secure the temperature probe
Step 3
Connect the electric heating belt and temperature probe to the controller.