FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
4 Installing Pre-fab. Modules
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
14
Preparations
Tools: safety helmet, safety belt, step ladder, protective gloves, utility knife
Materials: none
Skill requirement: common technician
Procedure
Step 1
Cut open the protective cover using a utility knife and remove the protective cover.
When removing the protective cover, take protective measures for working at heights.
----End
4.1.3 Hoisting and Securing Pre-fab. Modules
Prerequisites
To facilitate subsequent installation, ensure that pre-fab. modules are level after hoisting.
Select an appropriate crane based on standards of the crane company, and ask a
professional to assess the crane onsite.
The hoisting ropes are available.
The positions of pre-fab. module corner fittings are correctly marked.
The doors of pre-fab. modules to be hoisted are closed.
Ensure that the weather condition is good without wind when pre-fab. modules need to
be hoisted outdoors.
Context
The crane and steel ropes must meet the pre-fab. module hoisting requirements.
Table 4-1
Parameters for hoisting pre-fab. modules
Weight
Steel Rope
Length
Steel Rope
Quantity
Dimensions (H x W x D)
Net weight: <
6000 kg
> 6.5 m
4 PCS
2896 mm x 2438 mm x 6058 mm
Hoisting Precautions
Stage
Precautions