Procedure
1.
Power down the server (
on page 28).
2.
Remove the server (
on page 28).
3.
Place the server on a flat, level work surface.
4.
Remove the access panel (
on page 29).
5.
Open the front bracket.
NOTE:
Depending on the server configuration, the HPE Smart Storage Battery or the M.2 enablement
backplane might be installed on the front bracket.
Removing the air baffle
IMPORTANT:
The left and right sides of the chassis are oriented 180° from each other. Components
that are installed on one side of the chassis must be turned 180° when they are installed on the opposite
side.
Procedure
1.
Power down the server (
on page 28).
2.
Remove the server (
on page 28).
3.
Place the server on a flat, level work surface.
4.
Remove the access panel (
on page 29).
5.
on page 29).
6.
Remove the air baffle.
30
Removal and replacement procedures
Содержание ProLiant XL230k Gen10
Страница 5: ...Warranty information 72 Regulatory information 73 Documentation feedback 73 5...
Страница 22: ...22 Customer self repair...
Страница 23: ...Customer self repair 23...
Страница 24: ...24 Customer self repair...
Страница 25: ...Customer self repair 25...
Страница 49: ...6 Install the riser cover 7 Install the riser into the I O module Removal and replacement procedures 49...
Страница 61: ...Chassis server bay numbering Chassis I O module bay numbering Component identification 61...
Страница 65: ...Cabling Front panel LED board assembly cabling SATA drive cabling Cabling 65...