Space and airflow requirements
To allow for servicing and adequate airflow, observe the following space and airflow requirements when
deciding where to install a rack:
• Leave a minimum clearance of 63.5 cm (25 in) in front of the rack.
• Leave a minimum clearance of 76.2 cm (30 in) behind the rack.
• Leave a minimum clearance of 121.9 cm (48 in) from the back of the rack to the back of another rack
or row of racks.
Hewlett Packard Enterprise servers draw in cool air through the front door and expel warm air through the
rear door. Therefore, the front and rear rack doors must be adequately ventilated to allow ambient room
air to enter the cabinet, and the rear door must be adequately ventilated to allow the warm air to escape
from the cabinet.
CAUTION:
To prevent improper cooling and damage to the equipment, do not block the ventilation
openings.
When vertical space in the rack is not filled by a server or rack component, the gaps between the
components cause changes in airflow through the rack and across the servers. Cover all gaps with
blanking panels to maintain proper airflow.
CAUTION:
Always use blanking panels to fill empty vertical spaces in the rack. This arrangement
ensures proper airflow. Using a rack without blanking panels results in improper cooling that can
lead to thermal damage.
The 9000 and 10000 Series Racks provide proper server cooling from flow-through perforations in the
front and rear doors that provide 64 percent open area for ventilation.
CAUTION:
When using a Compaq branded 7000 series rack, install the high airflow rack door insert
(PN 327281-B21 for 42U rack, PN 157847-B21 for 22U rack) to provide proper front-to-back airflow
and cooling.
CAUTION:
If a third-party rack is used, observe the following additional requirements to ensure
adequate airflow and to prevent damage to the equipment:
• Front and rear doors—If the 42U rack includes closing front and rear doors, you must allow
5,350 sq cm (830 sq in) of holes evenly distributed from top to bottom to permit adequate airflow
(equivalent to the required 64 percent open area for ventilation).
• Side—The clearance between the installed rack component and the side panels of the rack must
be a minimum of 7 cm (2.75 in).
Temperature requirements
To ensure continued safe and reliable equipment operation, install or position the system in a well-
ventilated, climate-controlled environment.
The maximum recommended ambient operating temperature (TMRA) for most server products is 35°C
(95°F). The temperature in the room where the rack is located must not exceed 35°C (95°F).
Setup
35
Содержание ProLiant DL180
Страница 30: ...24 bay SFF hot plug drive model Fan bay numbering 30 Component identification...
Страница 58: ...SFF 4 Install the drive LFF SFF 58 Hardware options installation...
Страница 97: ...Secondary riser cage Slot 4 Slot 5 or 6 Hardware options installation 97...
Страница 112: ...Secondary riser cage Rear 2 bay SFF drive cage 10 Remove the nonredundant power supply 112 Hardware options installation...
Страница 127: ...Cable routing SFF drive model Box 1 to type a controller Box 1 to type p controller Cabling 127...
Страница 128: ...Box 2 to type a controller Box 2 to type p controller 128 Cabling...
Страница 129: ...Box 3 to system board Box 3 to type a controller Cabling 129...
Страница 130: ...Box 3 to type p controller 8 bay SFF power cable default 130 Cabling...
Страница 135: ...Mini SAS cable to SAS expander Cabling 135...
Страница 137: ...M 2 SSD enablement board installed in secondary riser Cabling 137...
Страница 141: ...Cable routing USB 3 0 Cable routing Power supply HPE 500W power supply cabling non hot plug Cabling 141...
Страница 142: ...Cable routing Serial port Cable routing iLO Service Port SFF LFF 142 Cabling...
Страница 144: ...Secondary riser cage Slot 4 Slot 5 or 6 144 Cabling...
Страница 145: ...Cable routing GPU Color Description Orange GPU power cable Blue Rear 2 bay SFF power cable Cabling 145...