Chapter 6: Scheduling Jobs
95
Note that Data Protector Express does NOT automatically update these fields when you manually “force”
a scheduled job to run. For example, when Data Protector Express automatically runs a scheduled backup
job on a Monday, it changes (updates) the
Backup Mode
from
Full
to
Incremental
. But when this job is
“forced” to run before its scheduled time, Data Protector Express does not automatically update these
fields.
Before forcing a failed job to run again, open the job log of the failed job, noting the appropriate options.
If needed, print the job log. Next, open the
Options
and
Device/Media
property pages of the failed job.
Set the settings on the options page to match those of the failed job. In particular, check the
Backup
mode
,
Write mode
,
New media location
,
New media name
and
Media
.
You will also want to select the appropriate media in the
Media
field on the
Device/Media
page. Use the
Browse
button to select the same media as the failed job was to use. When the options of the job match
the options the failed job would have used, run the job.
If you have changed the
Media
field, be certain that this field is set back to its original specification so
that scheduled jobs will automatically select the proper media.
An alternative method would be to copy the failed job, change the schedule type to
Not Scheduled
and
then set the options settings to match the failed job. Manually “force” the job to run and delete it after it
has successfully completed.
Scheduling a job to run once only
Turn off all the dates on the
Manual
schedule except the desired date.
When you want to run a job only once, you should set the
Schedule Type
field on the
Schedule page
to
Not scheduled
. Then you can run the job from the
Backup
,
Restore, Verify or Media
job views at any
time. If you need to run the job once during off-peak hours, you can set the
Schedule Type
field to
Run
on specific day
.
But what if you only need to run a job once during off-peak hours?
Create a new backup job that runs only once
1. From the Backup job view, create a new job.
2. When the
General
page appears, give it a name, such as
One-Time Backup
.
3. Open the
Selection
page and select the objects (directories, files, etc.) to back up. Consider selecting
the
Network
or computer name check boxes to back up all data on the computer or on the network.
4. Select
Run on specific day
in the
Schedule Type
field on the
Schedule
page.
5. Set the
Start time
and
Start Date
for the job.
6. Click
OK
to close the backup job properties window. The job will run once on the selected day at the
selected start time.
Scheduling simple backup jobs
Many computer users do not need the power of one of Data Protector Express’s default schedules. They
can manage their backups best with a simplified backup plan, such as the simple daily backup or the
simple five-day rotation described below.
Содержание BB118BV - StorageWorks Data Protector Express Package
Страница 1: ...U s e r s Gu i d ea n dT e c h n i c a l R e f e r e n c e ...
Страница 339: ......
Страница 345: ......
Страница 365: ...Index 347 ...