MAN0974-14-EN_XL7_XL7P_UM
July 6, 2022
Page 18 | 199
Once the panel design has been completed using the criteria and suggestions in the following sections,
use the following steps to panel mount the XL7/XL7 PRIME OCS.
1.
Remove all connectors from the XL7/XL7 PRIME OCS unit.
1.
Make sure the gasket is installed on the XL7/XL7 PRIME OCS and is free from dust and debris.
Check that the corners of the gasket are secure.
2.
Pass the unit through the panel.
3.
Insert each of the four (
4
) mounting clips into the slots in the XL7/XL7 PRIME OCS case. One clip
should be installed on each corner. Lightly tighten each screw so the clip is held in place.
4.
Tighten the screws on the clips such that the gasket is compressed against the panel.
Recommended torque is 7-10 in-lbs (0.8-1.13 Nm).
3.3
Mounting Orientation
3.3.1 XL7/XL7 PRIME OCS Mounting Clip
Figure 3.2
–
XL7/XL7 PRIME OCS with Mounting Clips
Slots for mounting clips