Commissioning
This chapter describes the commissioning of the system 6842.
3.1 General Procedure
The commissioning procedure is as follows:
•
Check the cabling:
o
Earth
o
Power supply
o
GPS antenna equipment
o
COM0 / COM1 serial interfaces
o
DCF77 antenna simulation (77.5kHz)
o
Error relays
o
Function Boards
•
Isolate all plug connections to the output interfaces and Function
Boards
(recommended)
•
GPS antenna equipment connection to remain in place
•
Switch on System 6842
•
Power LEDs light up on front and rear sides
•
The start frame appears on the display (for approx. 3 seconds)
•
Execute all parameter settings via the
SET menu
and also via the
INI
and
S.CLOCK menus
when necessary
•
Check for successful synchronization of the System 6842
•
Commission the Function Boards (where present):
o
Set the Function Board(s) parameters
o
Re-establish the plug connections
o
Check that the connected equipment is receiving the time correctly
3.2 Switching on the Operating Power Supply
AC power supply:
I O
Put the mains power switch into position "
I
" (on).
The System 6842 GPS Slim Line (1U) runs and the firmware version
and programming date are shown on the display
(see
Chapter 3.3 Display after System Start/Reset (Firmware)
).
DC power supply:
Switch on external power supply source.
The System 6842 GPS Slim Line (1U) runs and the firmware version
and programming date are shown on the display
(see
Chapter 3.3 Display after System Start/Reset (Firmware)
).
The Power Status LED and the red Sync LED light up on the front and rear sides for both
types of power supply.