26
Henrad CC FF
- Installation
1. Check the flue length measurement made in
Frame 10.
2. Use this dimension to mark the flue length,
starting from the groove, as illustrated.
3. To ensure a square cut, mark the flue all the way
round, using, e.g. a steel tape or paper strip with
the ends overlapped.
4. Cut to length, using the cardboard support aid.
5. Remove the cardboard offcuts and de-burr the
metal edges.
6. Mark round the air duct 10mm from the end.
7. Cut air duct only to be 10mm shorter than the
flue duct to allow for the engagement.
8. Clean and de-burr ends of ducts.
33 FIXING THE FLUE TO THE TURRET
1. Insert the flue into the prepared
hole. Refer to Frame 26 for details.
2. Mate the flue to the turret. Refer to
Frame 28 for details.
Note.
To facilitate turret fixing or removal do
NOT make good the wall.
32 CUTTING THE FLUE TO LENGTH
34 SERVICE CONNECTIONS
General Notes
1. As detailed in Frames 14 and 23/24 'Fitting the Wall
Mounting Frame', top entry pipework is an option, as well
as mounting from the bottom or through the wall.
If pipes are run vertically within the boiler back space
provided by optional stand-off channel positions they must
avoid any obstructions imposed by the channels and by a
rear facing flue, should this position be selected.
2. Horizontal connecting pipes, where used, must be run
outside the limits of the boiler casing.
INSTALLATION
INST
ALLA
TION