BRANCH LINE PIPING
Suction Line – All Defrosts
• Pitch in direction of flow.
• May be reduced by one size at one third of case run
load and again after the second third. Do NOT
reduce below evaporator connection size.
• Suction returns from evaporators enter at the top
of the branch line.
Liquid Line – Off-time and Electric Defrost
• May be reduced by one size after one half the case
load run. Do not reduce below
evaporator connection size.
• Take-offs to evaporators exit the bottom of the liq-
uid line. Provide an expansion loop for each evapo-
rator take-off (minimum 3 in. (76 mm) diameter).
Liquid Line – Koolgas Defrost
• Maximum of 6 evaporators per Branch System.
• Increase the liquid line size inside the case by two
sizes over the branch size.
Branch Size
In Case Size
1/2
7/8
5/8 1
1/8
7/8 1
3/8
1
1/8 1
5/8
1
3/8 2
1/8
• Take-offs to evaporators exit the bottom of the liq-
uid line. Provide an expansion loop for each evapo-
rator take-off (minimum 3 in. (76 mm) diameter).
The following information is applicable only
for piping Hussmann merchandisers to
Hussmann refrigeration equipment.