Regulating Unit PMR-06
Fax. ++39(0)438.200545
Author:
S.D.T. / KM
OPERATION
Editon: 12/2005
Page
D-12
Replaces: 05/2005
D.3.2.5
M
ANUAL USE OF THE
PMC-04
When the PMC-04 is connected to the PMR-06 regulating unit, the joining cycle is
managed as follows:
the PMR-06 regulating unit will manage the heating and thermosetting stages for the
time set.
When the time set has run out the cooling and compressed air blow stages pass to the
PMC-04 unit. The duration of the two stages is determined by the settings of the two
timers.
At the end of the air blowing stage it is necessary to press the STOP button on the
PMR-06 regulating unit to end the cycle and return to stand by.
ATTENTION
Pressing of STOP button during cooling phase or air blowing phase, using the cooling
unit PMC-04, cause an immediate stop of cycle and the change to the STAND-BY
status.
HINT:
In case cycle has been stopped during cooling phase, provide to remove water
from press circuit by starting a cycle with following parameters:
Upper
temperature:
65°C
Lower
temperature:
65°C
Welding
time: 5
sec.
Start cycle and wait till it stops itself, after air blowing phase.
Alternatively, clean water circuit manually with compressed air.
D.3.2.6
M
ANUAL USE OF THE EXTERNAL COOLING PUMP
The joining cycle is managed as follows:
the PMR-06 regulating unit will manage the heating and thermosetting stages for the
time set.
When the time set has run out, the PMR-06 regulating unit will activate the rear
electrical outlet the cooling pump is connected to get to
the cooling set point
temperature.
The removal of remaining water from tubes is carried out with a jet of compressed air.