3. Foundation Requirements
PNEG-1510
Top Dry 24', 30' and 36' Manual Batch
13
Duct and Drying Fan Pad Optional
Placement of the Duct Fan Pad: GSI Top Dry Duct System only.
Refer to
to determine the duct pad size.
1. The top of this pad should be level with the top of the bin’s foundation.
2. Recommended pad thickness is 4" minimum.
3. Front of pad should be perpendicular to bin wall.
Figure 3E
Содержание Top Dry 24
Страница 1: ...PNEG 1510 Top Dry 24 30 and 36 Manual Batch Construction and Owner s Manual PNEG 1510 Date 02 18 13 ...
Страница 2: ...2 PNEG 1510 Top Dry 24 30 and 36 Manual Batch ...
Страница 30: ...6 Stiffener Details 30 PNEG 1510 Top Dry 24 30 and 36 Manual Batch Outside Stiffeners Continued Figure 6A ...
Страница 34: ...6 Stiffener Details 34 PNEG 1510 Top Dry 24 30 and 36 Manual Batch Stiffener and Seam Locations Figure 6E ...
Страница 78: ...10 Accessories 78 PNEG 1510 Top Dry 24 30 and 36 Manual Batch 2 Ring Door Assembly Figure 10B ...
Страница 80: ...10 Accessories 80 PNEG 1510 Top Dry 24 30 and 36 Manual Batch Optional Bin Step Assembly WD 042 Figure 10C ...
Страница 82: ...82 PNEG 1510 Top Dry 24 30 and 36 Manual Batch NOTES ...