Installation of Outdoor Unit
型槽
型槽
Drainage ditch
Incline smoothly downward for 1/50 approx.
Construction method for anchoring bolt
Nut
Spring washer
Support
Screws protruding out
Type of anchoring bolt:JA
Size M12
4 bolts required
uilt on ground
When foundation is built on floor
Drainage ditch
A Viewa
Centralized Installation of Multiple Units
Notes:
1) Concrete proportioning: Cement: sand: stone = 1: 2: 4. Meanwhile, 10 pieces of
φ
10mm reinforced
steel bars shall be placed every 30mm.
2) Level the foundation surface with mortar and chamfer the sharp edge.
3) It is not needed to use gravel stone when the foundation is built on concrete floor, but the foundation
surface must be deburred.
4) Drainage ditch shall be built around the foundation, so that the condensate from the equipment can be
fully discharged.
5) To install the air conditioner on roof, please check the strength of building and take waterproof
measures.