Ducting System

To build an airtight and durable ducting system, we recom-

mend that the ducting system be made from spirally 

flanged pipes using fittings with a rubber ring seal.

To keep the noise level from the unit satisfactorily low, al-

ways mount silencers on the supply air and extract air duct-

ing systems between the unit and the first air intake and ex-

tract valves.

To prevent the air intake and extract valves from generating 

any noise, it is recommended that air speeds in the ducting 

be kept sufficiently low.

When place is found for fresh air and discharge air roof 

cowls/air gratings, avoid short-circuiting the two air 

streams so that the discharge air is sucked back in.

To achieve maximum comfort in the dwelling, it is recom-

mended that roof cowls/air gratings be placed on the north-

ern or eastern side of the building. 

Minimum distance be-

tween roof cowls/air gratings: 3 m.

Insulation of Ducts in Cold Spaces

To take advantage of the high recovery potential of the 

units (efficiency), it is necessary to insulate the ducts 

properly.

Genvex recommends, as follows:

Supply Air and Extract Air Ducts

To minimise heat loss from the ducting system in cold lofts, 

insulate the supply air and extract air ducts with a minimum 

of 100 mm insulation. If insulation form 

alternative (A) is used, it is recommended that it takes the 

form of 

two layers of 50 mm lamella mats with paper or foil exter-

nally and staggered joints between the two layers. If the 

ducts are laid on the rafter foot, 

alternative B may be used. The insulation must always be 

tightly packed around the ducts.

Fresh Air and Discharge Air Ducts 

It is recommended that fresh air and discharge air ducts be 

insulated with a minimum of 50 mm insulation followed by 

aluminium foil. The fresh air duct is insulated to prevent 

warm air in the loft from heating up the fresh air in the 

summer. 

To avoid condensation damage, make sure that the place 

where the discharge air duct passes through the roof or the 

gable end is sealed well.

Refer to your local distributor for guidance on 

national insulation directives.

Duct insulation, alt. A

Duct insulation, alt. B

Incorrect duct insulation

Содержание COMBI 185 BP

Страница 1: ...COMBI 185 BP INSTALLATION INSTRUCTIONS...

Страница 2: ...ater Sensor Anode 8 Electrical Installation 9 System Inspection and Fine Tuning 9 Optimal Fine Tuning of the System 9 Requirements to the Hot Water Circuit 9 Initial Operation of the Water Circuit 9 C...

Страница 3: ...erve all applicable laws and regulations The water used must be potable grade A reduction valve should be installed if the water pressure is high All connections for potable water must be certified No...

Страница 4: ...ed and as soon as the sensors detect a temperature drop in the tank The com pressor runs until the entire tank has once again reached the set temperature The Combi 185 will normally be able to satisfy...

Страница 5: ...relation to the existing water pressure and pressure loss The aspects of the installation that have to do with water must comply with the local HWS regulations The water pipes can either be made hard...

Страница 6: ...various connectors Fresh Air FRONT Discharge air Supply air Extract air Connecting Supply Air The ducting system leading from the unit to air injected in living quarters Connecting Extract Air The du...

Страница 7: ...tial of the units efficiency it is necessary to insulate the ducts properly Genvex recommends as follows Supply Air and Extract Air Ducts To minimise heat loss from the ducting system in cold lofts in...

Страница 8: ...ank is fitted with a 0 8 m2 heating coil The heat exchanger is enamelled externally The connection is 3 4 RG A sensor controlling external connections such as solar cells an oil burner or a wood burni...

Страница 9: ...7 turns depending on how close they are to the unit Optimal Fine Tuning of the System Use air measuring equipment Check that all 5 items in the section above have been carried out before performing t...

Страница 10: ...tional operational connection can be used if the function of the unit is to be supported by a wood burner or a solar collector installation Sensor T9 see the diagram on the next page measures the temp...

Страница 11: ...rne T5 T6 T8 T9 L8 Eksternt stop L9 Ikke i brug L10 Modulerende For Eftervarme L11 0 10V Motorventil Eftervarme 0 10V Ekstern bypass L16 Modbus L17 0 10V Udsugningsventilator 0 10V Indbl sningsventila...

Страница 12: ...air Sensor supply air External stop EC fan Extract air Blue Yellow EC fan Supply air Blue Yellow Control signal Motorvalve Reheating EC fan Extract air Power supply Motorvalve Reheating External Bypas...

Страница 13: ...2 Vv Varmespiral Kv T8 T7 T9 Solfanger T3 T4 T6 Betjeningspanel T5 T rrefilter Fordamper k leflade Indbl sning MA6 udligningsventil MA5 udligningsventil H jtryks pressostat Bypass T1 T2D T2S Compresso...

Страница 14: ...make sure that the maximum temperature of the do mestic hot water does not exceed 65 C and that the pres sure in the accessory heat exchanger does not exceed 3 bar Comply with all applicable local rul...

Страница 15: ...OPT 312 12 1 040384 Kompressorsamling 13 1 061014 Kompressor Large 13 1 061000 Kompressor small 14 1 045776 Anode Pos Qty Item number Description 1 1 069173 Bypass motor 2 1 045721 Heating element 3 1...

Страница 16: ...16 DECLARATION OF CONFORMITY The declaration of conformity can be found on our website www genvex com...

Страница 17: ...ilies At the same time our system is an important element when it comes to saving energy in homes and in society as a whole in fact you can recover up to 95 of the heat energy with a Genvex system All...

Отзывы: