The remote start signal may also be wired to one of the PM-PCs in 

addition to the PM-SC. This can be done so that at least one gen-

erator will start and connect to the Bus to provide critical power in 

the event that the PM-SC is unable to control the MPS. 
If the remote start signal from the ATS(s) fails, placing the PM-SC 

key switch in the MANUAL position will start the MPS as though a 

remote start command was received. All the units will parallel, per-

missives be issued, etc. This is a new feature. Previously, placing 

the PM-SC key switch in the MANUAL position had no function.

3.11.6  MANUAL BACKUP OPERATION

This mode of operation requires a trained operator to intervene in 

the event of a system failure. The manual backup operation is avail-

able with PM-PC and PM-SC firmware version 2.2H or later. The 

PM-PC touch screens must have screen firmware version 1.02 or 

later. The manual backup operation consists of the normal MPS 

operation with the added ability to manually request a generator to 

synchronize and connect to the Bus. If any of the generators are 

operating in a backup mode, the entire system changes to backup 

mode. When the MPS is in a backup mode, the communications 

are no longer adequate to provide dynamic power sharing between 

the connected generators while maintaining target frequency and 

voltage. All the generators attempt to take their share of the load. 

This results in the frequency varying by up to 3% and the volt-

age varying by up to 10% depending on the system load. Since 

the PM-SC does not have complete knowledge of the system in 

backup mode, it will not control the load shed signals and will only 

partially control the permissive signals. Therefore, the permissive 

signals must be manually operated and the load shed manually 

operated as needed. 
In addition to having the correct versions of firmware, the version 

of GenLink must be 2.8.0 or later to allow enabling of the manual 

backup feature.

Procedure for Enabling Manual Backup Operation:

Using GenLink, connect to the PM-SC.
Open the “Configuration” pull down menu and select “Regulator 

Settings” (Figure 3.10).

Figure 3.10 — Regular Settings

In the lower left corner of the “Regulator Settings Page” is a 

section called “Backup Paralleling Options”. Enable the “Manual 

Mode” setting (Figure 3.11).

Figure 3.11 — Enable Manual Mode

Close this window and drill down to each generator PM-PC and 

repeat this operation on each PM-PC. If the PM-PC(s) and the 

PM-SC are not set up the same, power will not be shared correctly 

while operating in backup mode.

Procedure for Entering Manual Backup Mode:

The following procedure refers to generator numbers. The genera-

tor number is the ModBus address of that generator. Backup mode 

priorities and delays are based on the generator numbers. Also, 

the wiring is specified based on the generator number. Therefore, 

the generators should be numbered sequentially via GenLink start-

ing at #1.
The MPS will normally have all PM-SC and PM-PC key switches in 

the AUTO position. If the PM-SC or any PM-PC is no longer com-

municating with the MPS, an alarm will indicate on the PM-SC, 

PM-PC, or both. This alerts the operator to the need for interven-

tion. If the utility power is lost at this time, the following procedure 

will allow the operator to put the MPS online manually.
When the utility fails, generator #1 should start if the remote start 

has been run to it and connect to the Bus when the generator is 

ready for load. If it does not, then start this procedure with genera-

tor #1.
Go to each generator in the MPS that is not running and turn the 

key switch to the OFF position.
After all the appropriate key switches are in the OFF position, each 

of these generators needs to have their key switch placed in the 

MANUAL position and the following touch screen procedure used 

to connect them to the Bus. This can be done by switching all 

these generators to MANUAL first then going back to connect each 

generator to the Bus or go to each generator, switch it to MANUAL 

and connect it to the Bus.
Using the generator touch screen main menu, select the Diagnostics 

page (Figure 3.12).

Operation

Содержание PowerManager 004975-2

Страница 1: ...MA 1 Enclosure Model 005039 1 NEMA 3R Enclosure Model 005047 1 NEMA 3R Enclosure with Heater PowerManager System Controller PM SC nOnly qualified electricians or contractors should attempt installatio...

Страница 2: ...munication Issues 9 3 10 Relay Functionality 9 3 11 Backup Modes of Operation 10 3 11 1 Introduction 10 3 11 2 Abbreviations 10 3 11 3 Documents 10 3 11 4 Standard Control System 10 3 11 5 Normal MPS...

Страница 3: ...az ard This symbol points out potential fire hazard This symbol points out potential electrical shock hazard The operator is responsible for proper and safe use of the equip ment The manufacturer stro...

Страница 4: ...Never work on the equipment when physically or mentally fatigued Inspect the generator s regularly and repair or replace all damaged or defective parts immediately Always use factory authorized parts...

Страница 5: ...to local state and national electrical and building codes Comply with regulations the Occupational Safety and Health Administration OSHA has established Also ensure that the generator s is installed...

Страница 6: ...ets with different power ratings Real time clock and calendar included user programmable to set exercisers based on date and time of day Monitoring set up of parameters and commands using New Generati...

Страница 7: ...the PC as well as Genlink this is supplied with the converter box Use the re direction software to select an unused port on your PC that will be re directed to the PC s LAN connection for example com...

Страница 8: ...ot set a leading power factor 3 1 7 SLAVE ADDRESS This is the Modbus slave ID of the generator and must correspond to the Modbus ID setting in the corresponding PM PC control panel Set all the paramet...

Страница 9: ...The base load can be programmed into the Kw setting field The power factor is fixed at 1 00 for exercise and cannot be adjusted 3 2 2 KW AND POWER FACTOR LIMITS These settings are only used to set up...

Страница 10: ...ecking any box Gen1 through 10 tells the system that the checked generator s has been intentionally taken out of service for example for maintenance The PM SC will then not expect that generator to st...

Страница 11: ...TION ISSUES Normally communication problems can be resolved with the help of either the Genlink or Touchscreen com port diagnostic displays see Figures 3 7 and 3 8 Select the diagnostic display then c...

Страница 12: ...g the generators to the bus proportion ally share load across all connected generators disconnect the generators from the Bus and shut the generators down The PM SC also accumulates data from the gene...

Страница 13: ...e for Enabling Manual Backup Operation Using GenLink connect to the PM SC Open the Configuration pull down menu and select Regulator Settings Figure 3 10 Figure 3 10 Regular Settings In the lower left...

Страница 14: ...Status After all the running generators are connected to the Bus the operator must determine what generator power is available and what the load requirements are If there is enough power available for...

Страница 15: ...procedure Go to each generator in the MPS that is in the MANUAL mode and using the generator touch screen main menu select the Diagnostics page Figure 3 17 Figure 3 17 Diagnostics Press the Cancel MA...

Страница 16: ...eration is available with PM PC and PM SC firmware version 2 2H or later Figure 3 20 The automatic backup operation consists of the normal MPS operation with the added ability of each generator PM PC...

Страница 17: ...er is available and what the maximum power needs are If there is enough power available for a given permissive to be active the PM PLS will activate the appropriate permissive signals If a generator s...

Страница 18: ...ch requests When the keyswitch is in the MAN position the PM SC will start the genera tors as though a two wire remote start had been issued This is to allow the system to be activated in the event th...

Страница 19: ...lax errors EITHER 1 Switch on the power to the unit 2 During the initialization phase a menu will appear briefly Press the CONFIG button 3 Now use the CALIBRATE button to calibrate the screen 4 Five c...

Страница 20: ...th the circuit diagram You should refer to this diagram to see that the correct input has operated Outputs from the controller are generally open collector This means that they sink current through a...

Страница 21: ...for customer use 5 User assigned 5 Free for customer use 6 User assigned 6 Free for customer use 7 Auto Led On Front Panel Led 8 User assigned 8 Free for customer use 9 Fault Led On Front Panel Led 1...

Страница 22: ...4 20ma User config channel 12 13 4 20ma User config channel 13 14 4 20ma User config channel 14 15 4 20ma User config channel 15 16 4 20ma User config channel 16 17 4 20ma User config channel 17 18 B...

Страница 23: ...E4086 in the back of this manual 1 Ensure that utility power is OFF at this point 2 Connect 18AWG or heavier double insulated wire fused at the source to terminals TB2 1 2 3 in the PM SC and run this...

Страница 24: ...tween generators should only have one end of the shield connected 7 Connect the standard telephone jack to a telephone line using an RJ 11 type cable 8 If an optional Annunciator is to be used connect...

Страница 25: ...23 Notes...

Страница 26: ...24 Notes...

Страница 27: ...25 Notes...

Страница 28: ...26 Installation Diagrams NEMA 1 Drawing No 0E7619 C...

Страница 29: ...27 NEMA 1 Drawing No 0E7619 C Installation Diagrams...

Страница 30: ...28 Installation Diagrams NEMA 3R Drawing No 0H3175 A...

Страница 31: ...29 NEMA 3R Drawing No 0H3175 A Installation Diagrams...

Страница 32: ...Parts shipment costs are reimbursed at ground shipment rates Costs related to requests for expedited shipping will be the responsibility of the customer 11 Verification of required maintenance may be...

Страница 33: ......

Страница 34: ......

Страница 35: ......

Страница 36: ......

Страница 37: ......

Страница 38: ......

Страница 39: ......

Страница 40: ......

Страница 41: ......

Страница 42: ......

Страница 43: ......

Страница 44: ......

Страница 45: ......

Страница 46: ...1 DECAL 24V SUPPLY 44 0E7438 1 DECAL POWER MANAGER SC TB6 45 062684 1 LUG SLDLSS 2 0 12 X 11 32 CU 46 067210A 1 DECAL GROUND LUG 47 091472 FT DUCT WIRING 1X1 5 6 FT 48 091472A FT COVER WIRE DUCT 1 IN...

Страница 47: ......

Страница 48: ......

Отзывы: