background image

 

37-1-615    Page  28 

PERIODIC INSPECTIONS

 

– A well-organized maintenance program will provide for periodic inspection of 

the blower, drive and components.  These inspections may prevent major repair and downtime. 
 

1. 

Observe the blower for vibration, heating, noise, oil seal leaks, and excessive shaft air leaks. 

 

2. 

Check for proper operation of the filters, coupling, drive, power unit, relief and check valves, 
gauges and other controls. 

 

3. 

Disconnect the drive and turn the blower by hand to check for drag, tight spots, bearing wear 
(radial and axial) and gear backlash.  Rotation should be free with no indication of drag or 
metallic interference. 

 

4. 

Inspect the interior through the inlet or discharge port for cleanliness, corrosion or parts 
contact. 

 

Rotating components will cause severe injury in case of personal contact.  Keep hands sway 
from the blower inlet and discharge ports. 

 

5. 

Check tightness of all screws and bolts. 

 

SOME COMMON CAUSES OF BLOWER FAILURE

 

 

1. 

Poor air filter maintenance or incorrect selection. 

 

2. 

Inadequate lubrication (wrong, dirty or low oil). 

 

3. 

Backflow of materials into the blower. 

 

4. 

Discharge pressure or inlet vacuum above blower rating. 

 

5. 

Blower speed below minimum rating. 

 

6. 

Blower speed too low for discharge pressure or inlet vacuum. 

 
BLOWER OVERHAUL

 

– Refer to Disassembly Section, page 36, and Assembly Section, page 40. 

 

REPAIR PARTS

 

– When ordering parts, specify Blower Model, Size and Serial Number. 

 
Reference numbers shown in the left hand column of the parts list are used to help locate parts shown on 
the drawing and sectional view.  DO NOT ORDER BY REFERENCE NUMBERS. 
 
After locating the reference number, the part number may be found for your particular blower under the 
correct Model Number Column.  Specify exactly the number of parts required (see column 

“Qty.”).  DO 

NOT ORDER BY SETS. 
 
 
 
 
 
 
 
 
 
 
Teflon is a register trademark of DuPont 
 
 

Содержание 9CDL R Series

Страница 1: ...PARTS LIST OPERATING AND SERVICE MANUAL BLOWERS VACUUM PUMPS 9CDL R SERIES 37 1 615 Version 05 August 30 2018...

Страница 2: ...d distributors provides the finest product support in the blower industry 1 Trained parts technical representatives to assist you in selecting the correct replacement parts 2 Complete inventory of new...

Страница 3: ...economical operation and minimum downtime Danger is used to indicate the presence of a hazard which will cause severe personal injury death or substantial property damage if the warning is ignored Wa...

Страница 4: ...st Of Illustrations 7 Safety Precautions 8 Introduction Your Key To Trouble Free Service 9 Section 1 Equipment Check 9 Section 2 Installation 10 Section 3 Operation 19 Section 4 Maintenance 25 Section...

Страница 5: ...encer 27 Oil Wetted Filter Silencer 26 Periodic Inspections 28 Repair Parts 28 Rotor Shaft Seals 27 Some Common Causes Of Blower Failure 28 Maintenance 23 Operating Principle 8 Operating Temperature 2...

Страница 6: ...OWER THE GATE ROTOR INTO THE HOUSING ASSEMBLY 40 FIGURE 7 5 ANGULAR CONTACT BEARING ASSEMBLY 41 FIGURE 7 6 BEARING INSTALLATION 41 FIGURE 7 7 DISCHARGE END BEARING CARRIER 42 FIGURE 7 8 ROTOR END CLEA...

Страница 7: ...has been relieved Electrical shock can and may be fatal Blower unit must be grounded in accordance with the National Electrical Code A ground jumper equal to the size of the equipment ground conductor...

Страница 8: ...y equipment necessary to protect personnel against hazards involved in installation and operation of this equipment in the system or facility STORAGE Your Gardner Denver Blower was packaged at the fac...

Страница 9: ...ies cross the discharge port completing the cycle The cycle occurs twice each revolution of the main bearing rotor and is continuous CONSTRUCTION All models of the 9CDL Series CycloBlower are of simil...

Страница 10: ...design cannot be given because of varying conditions If necessary use shims under feet for leveling to prevent distortion when foundation bolts are tightened After installation on the foundation is co...

Страница 11: ...k shaft and coupling bore for burrs Polish the shaft and bore if necessary for proper fit Fit keys to keyways Check coupling alignment Exact alignment will vary with the type of couplings however it i...

Страница 12: ...hould be positioned as close as possible to the drive cover This will reduce the overhung load and extend the bearing life On direct connected units alignment and lubrication of the couplings to speci...

Страница 13: ...37 1 615 Page 12 FIGURE 2 3 BELT DRIVE OVERHUNG LOAD CALCULATIONS...

Страница 14: ...bove maximum differential pressure rating of the blower for pressure service NOTICE Relief valves should be placed as close as possible to the blower inlet port vacuum operation or discharge port pres...

Страница 15: ...be provided near the blower discharge to indicate operation pressure If noise level is a factor a discharge silencer should be used The discharge line should be as straight as possible Where bends are...

Страница 16: ...37 1 615 Page 15 9CDL SERIES TOP INLET MAIN ROTOR DRIVE FIGURE 2 4 OUTLINE DIMENSIONS...

Страница 17: ...04 303CBP800 MODEL E INLET F DISCHARGE 9CDL13R 8 00 FLANGE 13 5 O D 8 HOLES 75 10 UNC TAP 11 75 DIA B C 8 00 FLANGE 13 5 O D 8 HOLES 75 10 UNC TAP 11 75 DIA B C 9CDL18R 10 00 FLANGE 16 O D 12 HOLES 8...

Страница 18: ...noise leaks and undue heating The blower will gradually heat up due to compression but after a reasonable length of time temperature will stabilize With very cold ambient conditions warm up blower at...

Страница 19: ...d on standard atmospheric discharge An accurate vacuum gauge and vacuum relief valve must be used as close to the blower inlet as possible Wet vacuum service employs a suitable liquid normally water i...

Страница 20: ...liquid rate on any size machine is shown in FIGURE 3 3 DO NOT EXCEED THIS Liquid Rate GPM 9CDL13 9CDL18 9CDL23 3 3 3 FIGURE 3 3 LIQUID RATE In applications where liquid carry over from the upstream sy...

Страница 21: ...ven pressures or vacuums are listed in FIGURE 3 6 as speed is reduced pressure or vacuum must also be reduced EXAMPLE Using a 9CDL13 blower operating against 18 PSIG minimum allowable speed is 1280 RP...

Страница 22: ...before restarting Do not operate a blower which is noisy vibrating or heating excessively Models Minimum Speed RPM Dry Pressure Up to 15 PSIG 18 PSIG 20 PSIG 9CDL13 1050 1280 1540 9CDL18 1050 1050 12...

Страница 23: ...which lead to premature failure 4 Be sure adequate drive guards are in place to protect the operator from severe personal injury from incidental contact 5 Check the unit for proper lubrication Proper...

Страница 24: ...THE BLOWER UNLESS OIL LEVEL IS AT THE MIDDLE OF THE SIGHT GAUGE Do not overfill Oil is added through the oil fill hole at the top of each bearing carrier RECOMMENDED LUBRICANT AEON PD Synthetic Blower...

Страница 25: ...rge Temperature Ambient Temperature Less than 10 F 10 F to 32 F 32 F to 90 F Greater than 90 F Less than 32 F 0 C ISO 100 ISO 100 32 F to 100 F 0 C to 38 C ISO 100 ISO 100 ISO 150 100 F to 225 F 38 C...

Страница 26: ...ng the air filters is one of the most important maintenance operations to be performed to insure long blower life Servicing frequency of filter elements is not time predictable A differential pressure...

Страница 27: ...nto the oil Upside down installation will result in heavy oil carryover 5 Replace the cover and tighten wing nut securely 6 Make sure all connections to the air filter are tight FIGURE 4 5 OIL WETTED...

Страница 28: ...carrier The grooved end of the spacer and the shaft seal bore have a close fit when cold When the blower reaches operating temperature for the first time the babbitt embeds slightly into the grooves f...

Страница 29: ...ds sway from the blower inlet and discharge ports 5 Check tightness of all screws and bolts SOME COMMON CAUSES OF BLOWER FAILURE 1 Poor air filter maintenance or incorrect selection 2 Inadequate lubri...

Страница 30: ...37 1 615 Page 29 SECTION 5 PARTS LIST FOR LIST OF PARTS SEE PAGES 32 33 303CBP810 00 Ref Drawing...

Страница 31: ...0037 8500037 17 SPACER BEARING 2 8504506 8504506 8504506 18 SEAL ROTOR SHAFT 2 8500390 8500390 8500390 19 SEAL ROTOR SHAFT 2 8500389 8500389 8500389 20 SHIM HOUSING 1 8502896 8502896 8502896 21 SHIM H...

Страница 32: ...56 WASHER LOCK 4 95B7 95B7 95B7 57 WASHER PLAIN 5 95W49 95W49 95W49 58 GASKET SEAL ADAPTOR 1 8500146 8500146 8500146 59 FOOT SUPPORT 1 8501089 8501089 8501089 60 FOOT SUPPORT 1 8502798 8502798 8502798...

Страница 33: ...Bearing Lock Nut 2 50Z15 Bearing Lock Nut 1 50Z12 Bearing Lock Washer 2 95N15 Bearing Lock Washer 1 95N12 Screw Socket Head Lock 4 75P12N Screw Socket Head Lock 16 75P6N Screw Socket Head Lock 5 75P2N...

Страница 34: ...n construction of some parts need cause no concern 1 Provide adaptor plate Figure 6 1 for pulling the gear hub 9 and for installation gate rotor bearings 29 32 NOTICE Numbers in parentheses refer to k...

Страница 35: ...t and lockwasher 33 35 A spanner wrench similar to that shown in FIGURE 6 3 should be made to prevent damaging the locknut This wrench is especially useful at assembly in saving time and more importan...

Страница 36: ...heat the pinion to aid in removal The pinion can be damaged by concentrated heat NOTICE Never reuse shaft seals that have been in operation Refer to Rotor Shaft Seal page 29 8 Remove the discharge end...

Страница 37: ...ound Handle with care to prevent burrs on rotors and housing Repeat Steps 9 and 10 on the second rotor 11 After removal of the rotors 2 3 rearrange blocking so the discharge end bearing carrier 5 hang...

Страница 38: ...ls with compliant lips but the hydrodynamic lip seals are made of Teflon and could be damaged by mishandling On the R Series the lip seals are not installed into the bearing carriers until after the r...

Страница 39: ...in the carrier with care Tighten the gear carrier 4 end bearing to housing 1 with screws 50 51 and lockwashers 55 evenly so the dowel pins will not be damaged 4 Coat the inside of both shaft seals 18...

Страница 40: ...nt slip bearings into the bore and install bearing retainer plate 11 12 FIGURE 7 6 Bearing must be assembled as directed in Step 6 Bearings are slip fit in the bore 6 The angular contact bearings 29 3...

Страница 41: ...f the rotor lobes 2 3 to the end of the housing 1 Rotate rotors to check each lobe and record the largest micrometer reading If the measurement varies more than 005 remove the rotors and check for bur...

Страница 42: ...e to dowel pin holes 12 With the dial indicator attached as shown in FIGURE 7 12 check the total end clearance Set the indicator on zero and lift the rotor with a hoist until the end of the rotor stri...

Страница 43: ...of the bearing spacer 17 Lightly coat the shaft extension and bearing bore with oil Assemble bearings as shown in FIGURE 7 5 on the shaft Assemble the press plates refer to FIGURE 6 1 and FIGURE 6 2...

Страница 44: ...s from the shim kit 94 as required to obtain the required calculated shim stack thickness at each screw location Using a micrometer measure each stacked shim thickness to insure the thickness is withi...

Страница 45: ...keyway for burrs Cover the shaft and keyway with the thin protective installation sleeve Push the oil seal 26 into the seal adaptor 25 Install the seal adaptor gasket 58 seal and adaptor to the end c...

Страница 46: ...ior to installation The third important measurement for clearance is to provide for floating bearings at the gear end 22 Turn the unit end for end gear end up With a depth micrometer on a perfectly fl...

Страница 47: ...tom of the oil channel cast inside of the bearing bore Remove installation sleeves 25 Slide enough shims 22 23 over the shafts FIGURE 7 24 up against the end of the bearing spacer 16 17 until the read...

Страница 48: ...the slot of the nut 33 holding the pinion Oil the bearings generously The final check to be made for running clearances is dividing the interlobe clearance of the rotors to prevent metal to metal cont...

Страница 49: ...eck for burrs or dirt on the rotors or gear teeth 30 FINDING SMALLEST PLUS READING FIGURE 7 29 Hold the gear under counterclockwise pressure to take up all slack and rotate the rotor clockwise two com...

Страница 50: ...side interlobe clearance and discharge end clearance When timing is completed remove the indicator button bracket and gear hub retainer plate Install the hub retainer plate 13 with pilot in the hub bo...

Страница 51: ...the Purchaser The Company may require the return of any part claimed not to be as warranted to on of its facilities as designated by Company transportation prepaid by Purchaser to establish a claim un...

Страница 52: ...For additional information contact your local representative or Gardner Denver Compressor Division 1800 Gardner Expressway Quincy Illinois 62301 Phone 800 682 9868 Fax 217 221 8780 E mail pd blowers...

Отзывы: