Figure II-4. High Current Cable.
5.
Connect the AC input power cable to the Remote TSP/NEG Control unit.
6.
Reconnect the AC input power cable to the DIGITEL MPC.
NOTE: If you need to connect a high current cable to the TSP/NEG unit, see Section 4,
Connecting a High Current Cable to TSP/NEG.
SAFE-CONN™ Installation on an Ion Pump
Use the following procedure to install a SAFE-CONN on the high-voltage feedthrough (HVFT)
of your ion pump.
Required Items
1.
Parts:
1.1.
a PEEK (Poly-Ether-Ether-Ketone) cylinder
1.2.
two SS rings
2.
Tools:
2.1.
two flat-head screwdrivers
2.2.
an SS installation tool and a plastic cylinder
Procedure
1.
Place SS ring #1 on the 10 kV HVFT (Figure II-5).
2.
Install the PEEK cylinder over the 10 kV HVFT with its inner diameter groove facing
away from the pump (Figure II-5). The inner diameter groove will locate/lock onto
the 10 kV HVFT tabs.
Figure II-5. SAFECONN Installation Diagram #1.
3.
Use the two flat-headed screwdrivers prying against the mini-CFF, pry SS ring #1
over the PEEK cylinder and into the open groove (Figure II-6).
4.
Using the SS installation tool and plastic cylinder, install SS ring #2 on the PEEK
cylinder.
4.1.
Place the SS ring on the nose/ramp of the SS installation tool.
Digitel MPC Manual
Page 13 of 72