
INSTALLATION - 2
Questions? Call (315) 298-5121, or visit us online at www.fulton.com
2-27
VSRT_IOM_2018-1213
3. Install the top fitting (the fitting without the
drain port) into the upper fitting on the water
bottle using service rated sealant. Wrench tighten
the fitting until it is snug and the glass outlet is
pointing at about 5 o’clock (about 1/8 turn from
its final downward vertical position).
4. Install the bottom fitting (the fitting with the
drain port) into the lower fitting on the water
bottle. Wrench tighten the fitting until it is snug
and the glass outlet is pointing directly upward.
5. Verify that the top and bottom fittings are
threaded into the water bottle tappings the same
amount (horizontally).
6. Remove the glass packing nut, friction washer
and glass packing from the fittings and place
them in the same order on either end of the water
gauge glass. Push both packings about 1in (25.4
mm) from the end of the water gauge glass.
7. Gently insert one end of the water gauge glass
into the top gauge fitting. Keeping the glass
inside the fitting, gently rotate the top fitting
clockwise until it is vertically aligned with the
bottom fitting.
It is crucial that the gauge
glass valves are aligned both vertically and
horizontally
.
If not aligned, they may leak.
8. Insert the gauge glass into the bottom fitting until
it bottoms out, and then gently raise glass about
1/16 in (1.6 mm). Do not allow glass to remain in
contact with any metal surface.
9. Carefully slide the bottom glass packing down
until the glass packing is touching the lower
gauge fitting. Carefully slide the top glass packing
up until the glass packing is touching the upper
gauge fitting.
10. Hand tighten both glass packing nuts, then
tighten ½ turn more by wrench. Do not over-
tighten. If any leakage occurs, tighten the packing
nut slightly, no more than a ¼ turn at a time, until
the leak stops.
11. When provided, install the protective guard over
the gauge glass assembly.
12. The gauge glass valves are fitted with ball checks.
Make sure that the valves are fully open to ensure
that the ball check will function properly in the
event that the gauge glass breaks.
13. Install drain piping from water bottle and lower
water gauge glass fitting to the boiler blow off
piping.
TOP GAUGE FITTING
VESSEL
WALL
GAUGE
GLASS
GLASS
PACKING
NUT
GLASS
PACKING
GUARD
ROD
PACKING
GLAND
(
OR
FRICTION
WASHER)
BOTTOM
GAUGE
FITTING
DRAIN
VALVE
BALL
CHECK
VALVE
ASME
AUTOMATIC
BALL
CHECK
VALVE
WASHER
Figure 14 - Sight Gauge Glass
Содержание VSRT 10
Страница 2: ......
Страница 5: ...1 1 Section Safety Warnings 1 Installation 2 Operation 3 Maintenance Troubleshooting 4 Warranty 5...
Страница 11: ...2 1 Section Safety Warnings 1 Installation 2 Operation 3 Maintenance Troubleshooting 4 Warranty 5...
Страница 44: ...2 INSTALLATION Fulton 2018 2 34 VSRT_IOM_2018 1213...
Страница 45: ...3 1 Section Safety Warnings 1 Installation 2 Operation 3 Maintenance Troubleshooting 4 Warranty 5...
Страница 61: ...4 1 Section Safety Warnings 1 Installation 2 Operation 3 Maintenance Troubleshooting 4 Warranty 5...
Страница 88: ...5 1 Section Safety Warnings 1 Installation 2 Operation 3 Maintenance Troubleshooting 4 Warranty 5 Parts 6...
Страница 89: ...5 WARRANTY Fulton 2018 5 2 VSRT_IOM_2018 1213...