3.8 EVAPORATION CHECKS
With the boiler running under normal load conditions, and the pump stopped having just completed
a refill cycle:
(a)
Ensure that the boiler water level is correct.
(b)
Switch the pump OFF at the pump interrupt / pump run switch.
The water level in the boiler will lower through natural evaporation. When the level nears the bottom of
the water level gauge sight glass, the first low water alarm will sound, the low water alarm lamp
will illuminate and the burner will shut down.
If it is required to check the second low water alarm, wait a further period for the LOW WATER RESET
switch to illuminate.
When the check is complete, proceed as follows:
(a)
Switch the pump ON at the pump interrupt / pump run switch.
(b)
Press the low water reset switch. The pump will start to refill the boiler.
If the pump starts to run at any time during the test then the test must be abandoned and restarted
from the beginning.
23
3.7 BLOWDOWN PROCEDURES (Daily tests) - continued.
Water gauge Blowdown
(a) Blowdown the water gauge, set 1.
1.
Open the gauge glass blowdown valve
A
2.
Close (for approx. 3 seconds) the top gauge valve
B
3.
Open valve
B
4.
Close (for approx. 3 seconds) the bottom gauge valve
C
5.
Open valve
C
6.
Close valve
A
Repeat for gauge set 2
On completion of the blowdown procedure ensure that all
isolation valves are OPEN and all blowdown valves CLOSED.
Note:
Where a Boiler is operating continuously at steam
pressure, advice should be taken from a Fulton agent
as to the appropriate blowdown procedure.
F03200
WORKING
POSITION
STEAM
BLOWDOWN
WATER
BLOWDOWN
Water Level Gauge operating positions.
A
C
Water Level Gauge
Set 1
Water Level Gauge
Set 2
B
C
B
B
B
C
C
A
A
A
3
Fig. 15 WATER LEVEL SIgHT gAUgE BLOWDOWN
Содержание 10J
Страница 42: ...J OIL E 08 2008...
Страница 56: ...J OIL E 08 2008 A0 2 1 BOILER OIL 1 2 3 4 5 6 December 12 2004...
Страница 74: ...J OIL E 08 2008 E1 6 1 WATER COLUMN 6 60 December 2004 E1 6 1 12 2004 1 11 6 4 2 9 10 4 6 4 5 3 8 7...
Страница 76: ...J OIL E 08 2008 F1 4 1 WATER LEVEL GAUGE ASSEMBLY 6 60 350mm and 300mm Clifton December 2004...
Страница 84: ...J OIL E 08 2008 H1 1 1 PUMP FEED WATER 1 December 2004...
Страница 86: ......