INZ-TN8ZSS-E
- 13 -
4.5 Setup procedure
Page
(1)
Installation site check
Check that the transmitter unit, the receiving unit, and the control unit are installed in a
location that meets the requirements. (“4. INSTALLATION”)
↓
(2)
Installation dimension check
Check that the transmitter unit and the receiver unit are installed in a manner that meets
the dimension requirements. (“4.2 Mounting dimensions”)
↓
(3)
Flange position check
Check that the companion flange for the transmitter unit and for the receiver unit are
installed in positions that meet the requirements. (“4.3 Mounting range of companion
flange”)
↓
(4)
Purging line check
Check that one 10/8 mm tube for purging, equipped with a flowmeter or a flow regula-
tor, is prepared for each of the transmitter unit and the receiver unit.
↓
(5)
Power supply and RS-485 wiring
Check that the power supply of rated voltage 100 to 240V AC ±10%, and rated fre-
quency 50/60Hz is prepared at the installation location for the control unit. Check the
wiring for RS-485 communication.
↓
(6)
Zero calibration
*If the analyzer has been turned off for a long time, warm-up the transmitter for about
90 minutes before calibration. (“6.1 Zero calibration”).
↓
(7)
Light intensity check
Take a memo of the output value from the probe for adjusting the received light intensity
during zero calibration. (“4.6 Received light ”)
↓
(8)
Span calibration
*If you feed any corrosive gas such as hydrogen chloride and carbon oxide, use the ex-
haust gas tube long enough and at an adequate position so that no one breathe in the
gas.
*Flow the zero gas after span calibration. (“6.2 Span calibration”)
↓
(9)
Angle adjustment
Attach the angle adjustment unit on each companion flange. Adjust the angle of the
transmitter unit and the receiver unit. (“4.7.3 Adjustment procedure”)
↓
(10)
Installation of purging equipment
↓
(11)
Installation of the transmitter box and the receiver box
(“4.9 Installation of the transmitter box and the receiver box”)
↓
Содержание ZSS-8 Series
Страница 1: ......
Страница 13: ...INZ TN8ZSS E 3...
Страница 16: ...6 INZ TN8ZSS E 3 2 Wiring diagram Input output terminal...
Страница 17: ...INZ TN8ZSS E 7...
Страница 29: ...INZ TN8ZSS E 19 4 8 Piping system diagram Fig 4 9...
Страница 42: ...32 INZ TN8ZSS E 5 2 Screen configuration...
Страница 57: ...INZ TN8ZSS E 47 About Span Calibration...
Страница 76: ...66 INZ TN8ZSS E...
Страница 111: ...INZ TN8ZSS E 101 APPENDIX 2 CODE SYMBOLS...
Страница 118: ...108 INZ TN8ZSS E DIMENSIONS IN MM...
Страница 119: ......