HEIGHT ADJUSTMENT ON OVEN
There is a 1 1/2” height adjustment on these models. (see
figure 3) With this adjustment and a 1/2” trim overhang, a
unit can be installed in existing openings 37 1/2” to 39” high
(1 1/2 cavity).
Figure 3
To adjust oven height:
A.
Lay oven on its back. (see figure 4).
B.
Remove the 6 screws that fasten the side extension
panel to the bottom sides of the oven.
C.
Move each panel down to the position that increase
the oven height to fit your opening. Each position changes
oven height approximately 1/2”.
D.
Line up the appropriate holes in the side extension
panels and sides of the oven. Replace the 6 screws.
E.
Proceed with oven installation. Return oven to upright
position.
4
Figure 4
CONNECT THE OVEN TO GAS
Figure 5
If flexible gas connector is used, gas line must be
AGA design certified.
Install a manual shutoff valve
in the gas line in an easily
accessible location outside of the oven. Be sure you know
how and where to shut off gas supply to the oven.
Check for leaks.
After connecting the oven to gas, check
the system for leaks with a manometer. If a manometer is
not available, turn the gas supply on to the oven and use a
liquid leak detector at all joints and connections to check for
leaks.
Tighten all connections
if necessary to prevent gas
leakage in the oven or supply line.
IMPORTANT:
A pipe joint sealant resistant to the action
of LP gas, must be employed on the pipe connections.
MTG. SCREW
MTG. SCREW
MTG. SCREW
MTG. SCREW
LOWER VENT GRILL
Figure 2
OVEN DOOR
OVEN BOTTOM
EXTENSION
PANEL
SHUT-OFF
VALVE
PRESSURE REGULATOR
OVEN
SAFETY VALVE
SHUT-OFF VALVE
3/8” NIPPLE
ADAPTOR
OR UNION
EXTERNAL
SHUT-OFF VALVE
SOLID PIPE
OR FLEX
CONNECTOR
ADJUSTMENT
HOLES
EXTENSION
PANEL
MOUNTING
SCREWS