Commissioning
A requirement for the following commissioning of the MS6(N)-SV-...-E-ASIS is assignment of a slave
address that is not safety-oriented and an address of a safety-oriented slave.
Note
Observe the sequence for error-free commissioning.
1. Apply operating pressure p1.
2. Switch on AS-i operating voltage. The MS6(N)-SV-...-E-ASIS automatically tests itself for errors.
•
LED AS-i lights up green.
•
Status LED
–
flashes green after successful self test.
–
flashes red, operating pressure p1 lacking or lies outside the permissible range
(
14.2 General data)
–
permanently lit red in case of a faulty self test (
13.2 Troubleshooting).
If the self test was successful, compressed air is briefly vented at the silencer.
The MS6(N)-SV-…-E-ASIS can be pressurized.
Note
The valve is tested pneumatically in a self-test once an hour for as long as the product
remains in this status.
3. Generate safety-oriented AS-i telegram through the AS-i safety monitor.
The MS6(N)-SV-…-E-ASIS switches into the pressurized status.
The LED status is permanently lit green.
Output pressure p2 is built up slowly.
The duration “t” of the pressure build-up is adjusted using the flow control screw attached to
the cap. The output pressure rises corresponding to the set throttle point (
14.4 Filling flow ).
When the switch-through pressure is reached (approx. 50 % of operating pressure p1), the
valve’s main seat opens (
14.3 Switch-through pressure / filling time ). Das
MS6(N)-SV-...-E-ASIS is ready for operation (safety function safe venting).
No further settings are required.
Содержание MS6-SV-***-E-ASIS Series
Страница 30: ...MS6 N SV E ASIS 30 Festo MS6 N SV E ASIS 1205NH Deutsch...
Страница 58: ...MS6 N SV E ASIS 58 Festo MS6 N SV E ASIS 1205NH English...
Страница 59: ......