49
INSTALLATION OF INS
Dome
WITH
the Skylight Window:
1. Start the installation of the Ins from Level 2 and work your way down.
2. Install all panels on Level 2 before installing the level below. Pay attention to the correct positioning of the
panels - panels with ventilation openings need to be in line with the vents in the dome cover.
3. Once complete, move to Level 3. Undo the bottom bolts from Level 2 and place the next layer of insulation
on top of the previously installed level 2. The top of level 3 will overlap the bottom of level 2. Pay attention
to the correct positioning of the panels - panels with porthole openings need to be in line with the
porthole openings in the dome cover.
4. Repeat the process until you finish with Level 5.
5. The remaining panel from Level1 can be installed at a later date, when needed.
Level 1 Insulation can be
added later. To cover
the skylight window
Level 1
Level 2
Level 3
Level 4
Level 5
Level 2
Level 3
Level 4
Level 5
Level 1
Ins
/ Skylight Window
Drawing 28
Ins Cross-section
- Dome with Skylight Window