Installation
The system must be monitored after initial start-
up for a minimum of 60 minutes to ensure proper
operating characteristics such as:
• Proper metering device operation and desired
super heat readings,
• Suction and discharge pressure are within
acceptable levels,
• Correct oil level in compressor sump indicating
proper oil return,
• Low foaming in sight glass and compressor
sump temperature 10 K above saturation
temperature to show that there is no refrigerant
migration taking place,
• Acceptable cycling rate of compressors,
including duration of run times,
• Current draw of individual compressors within
acceptable values (max. operating current),
• No abnormal vibrations and noise.
Commissioning
Oil level checking and
top-up
In installations with good oil return and line
runs up to 20 m, no additional oil is required. If
installation lines exceed 20 m, additional oil may
be needed. 1 or 2% of the total system refrigerant
charge (in weight) can be used to roughly define
the required oil top-up quantity but in any case
the oil charge has to be adjusted based on the oil
level in the compressor sight glass.
When the compressor is running under stabilized
conditions the oil level must be visible in the
sight glass.
The presence of foam filling in the sight glass
indicates large concentration of refrigerant in the
oil and / or presence of liquid returning to the
compressor.
The oil level can also be checked a few minutes
after the compressor stops.
When the compressor is off, the level in the
sight glass can be influenced by the presence of
refrigerant in the oil.
Always use original Danfoss oil from new cans.
Compressor series
Oil
SM
Mineral oil 160P
SY
P.O.E. 320 SZ
SZ
P.O.E. 160 SZ
Top-up the oil while the compressor is idle. Use
the schrader connector or any other accessible
connector on the compressor suction line and
a suitable pump. See News bulletin “Lubricants
filling in instructions for Danfoss Commercial
Compressors”.
Insulation resistance and
dielectric strength
Insulation resistance must be higher than 1
megohm when measured with a 500 volt direct
current megohm tester.
Each compressor motor is tested at the factory
with a high potential voltage (hi-pot) that
exceeds the UL requirement both in potential
and in duration. Leakage current is less than
5 mA.
SM/SY/SZ scroll compressors are configured
with the pump assembly at the top of the shell,
and the motor below. As a result, the motor
can be partially immersed in refrigerant and
oil. The presence of refrigerant around the
motor windings will result in lower resistance
values to ground and higher leakage current
readings. Such readings do not indicate a faulty
compressor.
In testing insulation resistance, Danfoss
recommends that the system be first operated
briefly to distribute refrigerant throughout the
system. Following this brief operation, retest the
compressor for insulation resistance or current
leakage.
Never reset a breaker or replace a fuse without
first checking for a ground fault (a short circuit to
ground). Be alert for sounds of arcing inside the
compressor.
Vacuum or charge from one side can seal the
scrolls and result in a non-starting compressor.
When servicing, always ensure that LP/HP
pressures are balanced before starting the
compressor.
Be sure to follow all government regulations
regarding refrigerant reclamation and
storage. For more detailed information, see
“Recommended refrigerant system charging
practice” news bulletin FRCC.EN.050.
45
FRCC.PC.003.B4.02
Application Guidelines
Содержание Danfoss Maneurop MT
Страница 2: ......
Страница 3: ......
Страница 39: ......
Страница 42: ......
Страница 43: ......
Страница 65: ......
Страница 66: ......
Страница 67: ......
Страница 103: ......
Страница 105: ...Maneurop reciprocating compressors NTZ R404A R507 60 Hz Application guidelines http danfoss us com...
Страница 106: ......
Страница 138: ......
Страница 139: ......
Страница 192: ......
Страница 193: ......
Страница 196: ......
Страница 239: ...Danfoss scroll compressors SM SY SZ R22 R407C R134a R404A R507A 50 60 Hz Application guidelines http cc danfoss com...
Страница 240: ......