SOLAR PANEL TOP POLE MOUNT
ASSEMBLY INSTRUCTIONS (cont.)
INSTALLATION RECOMMENDATIONS
•
Auger hole to minimum depth shown in Table 2.
• 6" of hole should be filled with crushed rock or blocking. This will
prevent the pipe from touching the base of the hole, insuring complete
encapsulation of the pipe when concrete is poured, as well as allowing
for water drainage. See Fig. 1.
•
Pipe should be installed vertically no matter the slope of the install site.
•
Make arrangements to prevent the pipe from twisting prior to pouring
concrete.
•
Pipe should be braced to remain plumb until concrete has cured (at
least 24 hours).
FIGURE 1:
Top of Pole Foundation Guideline Diagram
Page 10