Operation Instruction of BS Series Solar Pumping Inverter
Operation Control
30
Operation
Description
Display
↓
↓
↓
Turn off the DC switch,
waiting the LCD display off,
then turn on the DC
switch, the inverter will
auto-start to drive
pump(5.5kW)
3. After finishing all parameter settings, turn off Q2 of DC switch. After display screen is OFF for
5 minutes, turn on AC output. Then turn on DC input switch Q2. Wait for 60s. The machine will
operate automatically.
3.4.2 Procedure of Power Supply Debugging of Power Grid (Diesel Engine)
1. Conduct wiring according to systematic diagram and check whether the wiring is correct.