Battery Installation
1.
Before starting, ensure the enclosure is securely fixed (wall mounted or floor mounted) as per
above instructions.
2.
Ensure all internal covers are still attached
3.
Ensure all Circuit breakers are off, and the unit is completely isolated from mains and PV
4.
Specifically, ensure that the integrated battery circuit breaker is turned OFF to ensure isolation.
Figure 5: Unit before installing batteries
5.
Fit the battery modules in the below order, ensuring not to trap any wires behind each module
and to fix the module before fitting the next module, using the long M6 bolts provided, tighten
to approximately 1N.m
a.
ASYH006 - bottom left
b.
ASYH007
–
bottom right
c.
ASYH004
–
middle left
d.
ASYH005
–
middle right
e.
ASYH002
–
top left
f.
ASYH003
–
top right
6.
Tighten all the 24 mounting bolts to 5N.m +/- 1N.m
7.
Connect the fuel gauge temperature sensor from battery 6 to the master BMS as shown below