12.21.5
Assembling analysis cell
Figure 12-22: Assembling Analysis Cell
A. Cell lid
B. Cell lid fasteners
C. Cell lid insulation
D. Tube fitting nut
E. Bracket
F. Pressure sensor
G. Bracket fastener
H. O-ring
Procedure
1. Fit the O-ring (H) to the cell lid (A).
2. Fit the cell lid (A) to the analysis cell using the cell lid fasteners (B).
3. Pass the cell lid insulation (C) over the bracket before attaching the bracket (E) to
the cell lid using the bracket fastener (G).
4. Reattach the tube fitting nut (D) to the pipe adaptor.
5. Fit the cell lid Insulation into position and secure using the Velcro flaps.
Reference Manual
Repair and replacement
00809-0100-4512
October 2019
Reference Manual
161
Содержание Rosemount CT5100
Страница 1: ...Reference Manual 00809 0100 4512 Rev AA October 2019 Rosemount CT5100 Ex Continuous Gas Analyzer ...
Страница 16: ...16 ...
Страница 20: ...Contents Reference Manual October 2019 00809 0100 4512 xx Rosemount CT5100 Ex ...
Страница 28: ...Theory of operation Reference Manual October 2019 00809 0100 4512 28 Rosemount CT5100 Ex ...
Страница 46: ...Specifications Reference Manual October 2019 00809 0100 4512 46 Rosemount CT5100 Ex ...
Страница 66: ...Install Reference Manual October 2019 00809 0100 4512 66 Rosemount CT5100 Ex ...
Страница 84: ...Start up procedure Reference Manual October 2019 00809 0100 4512 84 Rosemount CT5100 Ex ...
Страница 92: ...Shutdown procedure Reference Manual October 2019 00809 0100 4512 92 Rosemount CT5100 Ex ...
Страница 112: ...Gas calibration Reference Manual October 2019 00809 0100 4512 112 Rosemount CT5100 Ex ...
Страница 172: ...ATEX IECEX assessment report summary Reference Manual October 2019 00809 0100 4512 172 Rosemount CT5100 Ex ...