EM TEST
PFS 200 Series
Manual for Operation
V 3.08
8 / 34
1
Test supply OUTPUT
2
Test supply PF1
3
Reference ground connection
4
Test supply PF2
5
Ventilation
6
Control voltage 0-10V
7
Ext. Trigger
8
Mains selector
9
Power on switch
10
Parallel interface
11
Serial interface
12
CN interface not used
13
Fail detection Fail1 / 2
10 Parallel interface
GPIB / IEEE-488 interface.
11 USB interface
USB interface “USB B” connector. For datatransfer a USB interface is available. The internal RS 232 interface is
converted to USB standard. Therefore the user must set the same Baudrate in the device and control software.
Using the USB interface the user can have emc problems during burst tests Our experiences says, that usually
the computer USB port is disturbed by interference’s. Therefore a high quality USB cable ( USB 2.0 standard)
must be used.
12 CN interface
Device internal interface not used
13 Fail detection FAIL 1 (TEST STOP)
The BNC input FAIL 1 can be used for failure detection at the EUT. If the input is set to ground (chassis) the
PFS-generator will be stopped and the actual test routine is finished. It is not possible to continue this test
routine. A complete restart of the routine is necessary.
A message of FAIL 1 is indicated in the LCD display as well as in the ISM software.
Fail detection FAIL 2 (TEST PAUSE)
The BNC input FAIL 2 can be used for failure detection at the EUT. If the input is set to ground (chassis) the
actual test routine is paused as long as the low level signal is available at the FAIL 2 input.
Without the low level signal the test procedure continues automatically.
A message of FAIL 2 is indicated in the LCD display as well as in the ISM software.
Rearside PFS200N150 or PFS200N200