APPENDIX A - CONTROL MODULE

Table 7 - Troubleshooting Error Codes

Error 

Code 

Number

Defi nition

Consequence

4

Flame current too low. Check for 

fl

 ame.

Non critical alarm

6

Flame sensed out of normal sequence (before opening or after closing gas 

valve).

Soft lockout

18

Gas valve relays welded. Five consecutive soft lockouts.

Hard lockout

23

Flame sensed during prepurge ( before gas valve signaled opened).

Soft lockout

32

Sensor  1  error.    Temperature  sensor  in  well  is  not  reading  correctly.                       

Verify it is connected to board.  Replace if necessary.

Wait for recovery

55

Atmospheric damper end switch failed to close (end switch contacts stuck 

open).

Wait for recovery

56

Atmospheric damper end switch failed to open (end switch contacts stuck 

close).

Wait for recovery

57

Igniter 

fl

 ame rod shorted to burner ground

Wait for recovery

58

Igniter 

fl

 ame rod shorted to burner ground.  Repair or replace igniter.

Wait for recovery

59

Line Voltage error - voltage out of speci

fi

 cation high or low (15-37V (44-

66Hz))

Wait for recovery

60

Applies only to thermostats having on-board transformer.  

Polarity is wrong in this case.

Wait for recovery

Thermostat input higher than threshold.

61

Line voltage unstable - possibly too may heavy loads switching on and off 

causing erratic supply voltage.

Wait for recovery

62

Soft lockout: maximum number of retries exceeded.

Soft lockout

Soft lockout is reset after one hour if alarm reason disappears.

63

Soft lockout: maximum number of recycles exceeded.

Soft lockout

64

Soft Lockout - electronics failure. On-board self diagnostics detected error.

Soft lockout

65

Over temperature error.  Sensor measured temperature in excess of 

maximum allowable limit.

Soft lockout

 Note: Soft lockout time is 1 hour or manual reset. Hard lockout requires manual reset.

A.9 Intermittent Pilot

Ignition System Checks

STEP 1: 

Check ignition cable.

Verify ignition cable does not run in contact with 

• 

metal surfaces.
Verify only factory supplied Ignition cable (or 

• 

approved replacement) is used.
Verify connections to ignition module and igniter or 

• 

igniter-sensor are clean and tight.
Verify ignition cable provides good electrical 

• 

continuity.

STEP 2:

Verify ignition system grounding. Nuisance shutdowns 

are often caused poor or erratic grounding.

Common ground is required for module and pilot  

burner/igniter sensor.

— Check for good metal-to-metal contact between

  pilot burner bracket and the main burner.

— Check ground lead from GND (BURNER) terminal 

on module to pilot burner.  Verify connections 

are clean and tight. If wire is damaged or 

deteriorated, replace with No. 14-18 gauge, 

moisture-resistant, thermoplastic insulated wire 

with 105°C [221°F] minimum rating.

— Check ceramic 

fl

 ame rod insulator for cracks or 

evidence of exposure to extreme heat, which can 

permit leakage to ground. Replace pilot burner/

igniter sensor and provide shield if necessary.

— If 

fl

 ame rod or bracket is bent out of position, 

restore to correct position.

Содержание Columbia MCC II Series

Страница 1: ...ATION OPERATION MAINTENANCE MANUAL Models MCC 8D MCC 8DP MCC 9D MCC 9DP Tested For 50 psi ASME Working Pressure COLUMBIA BOILER COMPANY Main offices and Factory Pottstown PA Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com ...

Страница 2: ...2 1 DIMENSIONS Table 1 Dimensions BOILER MODEL NUMBER DIMENSIONS INCH FLUE DIAMETER A WIDTH MCC 8 7 27 MCC 9 7 30 Add 5 to height for vent Damper Figure 1 Dimensions ...

Страница 3: ...ensive piping systems etc 3 MBH 1 000 Btuh British Thermal Unit Per Hour Ratings marked Net AHRI Ratings indicate amount of remaining heat input used to heat radiation or termi nal units Net AHRI Ratings shown are based on allowance of 1 15 in accordance with factors shown on AHRI Standard as published by The Hydronics Institute Selection of boiler size should be based upon Net AHRI Rating being e...

Страница 4: ...y Read this manual and understand all requirements before beginning installation SAFETY SYMBOLS WARNINGS The following defined symbols are used throughout this manual to notify the reader of potential hazards of varying risk levels NOTICE Used to address practices not related to personal injury CAUTION Indicates a hazardous situation which if not avoided could result in minor or moderate injury WA...

Страница 5: ...ence of such requirements to the National Fuel Gas Code ANSI Z223 1 NFPA 54 Where required by the authority having 2 jurisdiction the installation must conform to the Standard for Controls and Safety Devices for Automatically fired Boilers ANSI ASME CSD 1 Boiler series is classified as a Category I Vent 3 installation shall be in accordance with Venting of Equipment of the National Fuel Gas Code A...

Страница 6: ...ultiple appliances Do not use an air infiltration rate ACH greater than 0 60 Volume 21 ft3 ACH x Total Input Mbh Refer to National Fuel Gas Code for opening C requirements between connected indoor spaces All Outdoor Air Provide permanent opening s communicating directly or by ducts with outdoors Two Permanent Opening Method Provide A opening commencing within 12 inches of top and second opening co...

Страница 7: ... of the relief valve outlet over the entire length of discharge line have no intervening shutoff valve between safety relief valve and discharge to atmosphere do not plug or place any obstruction in discharge line terminate freely to atmosphere where any discharge will be clearly visible and at no risk of freezing allow complete drainage of the valve and the discharge line be independently support...

Страница 8: ...heating boiler Appropriate valves must be used to prevent chilled medium from entering heating boiler See Figure 5 page 9 B Boiler connected to heating coils located in air handling units where they may be exposed to refrigerated air circulation piping system shall be equipped with flow control valves or other automatic means to prevent gravity circulation of boiler water during cooling cycle LOW ...

Страница 9: ...9 Figure 5 Chilled Water Piping Figure 4 Typical Hot Water Piping 6 CONNECTING SUPPLY AND RETURN PIPING ...

Страница 10: ...10 Figure 6 BYPASS PIPING CIRCULATOR ON SUPPLY Figure 7 BYPASS PIPING CIRCULATOR ON RETURN Bypass Piping Required For High Mass Large Water Content Systems 6 CONNECTING SUPPLY AND RETURN PIPING ...

Страница 11: ...d by using plug supplied with vent damper Position furnished vent damper on top of flue 1 outlet collar Fasten damper securely to flue outlet collar with sheet metal screws Verify damper blade has clearance to operate inside of diverter Do not modify either draft diverter or vent damper during installation As An Option Damper may be installed in any horizontal or vertical position closer to flue o...

Страница 12: ...ny appliance not connected to the common venting system Turn on any exhaust fans such as range hoods and bathroom exhausts so they will operate at maximum speed Do not operate a summer exhaust fan Close fireplace dampers 7 CHIMNEY AND VENT PIPE CONNECTION Place in operation the appliance being inspected 4 Follow the lighting instructions Adjust thermostat so appliance will operate continuously Tes...

Страница 13: ...er indicator points to open position Turn thermostat or controller down again and check damper position indicator returns to closed position Vent Damper Manual Operation Vent damper may be placed in open position to permit burner operation by using HOLD DAMPER OPEN switch located on damper controller Thermostat will control burner firing as before while damper will remain open DO NOT turn damper o...

Страница 14: ...aller Two stage regulation should be used by propane installer Propane gas piping should be checked out by propane installer CHECKING GAS PIPING DANGER Fire Hazard Do not use matches candles open flames or other methods providing ignition source Failure to comply will result in death or serious injury Pressure test boiler and gas connection before placing boiler in operation Pressure test over 1 2...

Страница 15: ...tures televisions a fireplace or a chimney Check thermostat operation by raising and 4 lowering thermostat setting as required to start and stop the burners Instructions for the final adjustment of the 5 thermostat are packaged with the thermostat adjusting heating anticipator calibration etc Set heat anticipator at 2 amps 24 volt thermostat connects to aquastat terminals T and TV WARNING Electric...

Страница 16: ...Integrated High Limit Electronic Ignition Control 240008781 I Inducer is not an option WARNING Modification substitution or elimination of factory equipped supplied or specified components may result in personal injury or loss of life ...

Страница 17: ...17 11 WIRING DIAGRAMS Figure 13 Integrated High Limit Electronic Ignition Control 240008781 ...

Страница 18: ...18 11 WIRING DIAGRAMS Figure 14 Integrated High Limit Electronic Ignition Control 240008781 ...

Страница 19: ...d repeat this process Repeat until you have covered every radiation units in the system ending up at highest unit in system If your units have automatic vents manual venting is unnecessary but it will speed up the proper filling of your system If your system is closed expansion tank system you may leave it open to refill system automatically as needed Check temperature pressure gauge Not position ...

Страница 20: ...lockwise to OFF Do not force WARNING If you do not follow these instructions exactly a fire or explosion may result causing property damage personal injury or loss of life This appliance is equipped with an ignition device which automatically lights burner Do NOT try to light this burner by hand Before operating smell all around appliance area for gas Be sure to smell next to floor because some ga...

Страница 21: ...t be functioning properly to permit operation Safety lockout system has to be reset by turning thermostat to lowest setting for one minute then back to normal setting ADJUST PILOT BURNER Pilot flame should surround 3 8 to 1 2 of the pilot sensor See Figure 16 If flame needs adjusting do it as follows Remove screw cover over pilot adjusting screw 1 Insert small screwdriver and adjust flame as 2 nee...

Страница 22: ...w degrees After setting limit control to limit setting C check to see if it shuts off gas supply to burners Turn your thermostat up to call for heat and let boiler run until temperature of water reaches limit setting Gas valve should shut off and circulator running until thermostat is satisfied or water cools enough to restart burners through limit control Set thermostat for desired temperature D ...

Страница 23: ...NT PIPE Venting and piping should be checked at least once a season If vent piping shows any sign of leaking replace immediately WATER SYSTEM If system is to remain out of service during freezing weather always drain it completely water left in to freeze will crack pipes and or boiler CLEANING YOUR BOILER AND BURNERS Flue passages between sections should be examined yearly and cleaned if necessary...

Страница 24: ...minals and wire joints Rollout switch blown Have your service agent check heat exchanged for blockage Replace rollout switch with exact replacement Spill switch blown Have your service agent check venting system and chimney for blockage or down draft condition Reset spill switch Vent damper not operating Consult troubleshooting guide in Effikal manual packaged with vent damper Possible Cause What ...

Страница 25: ...nstalled in supply line It will eliminate air from water before it reaches radiators and bleed off this air MAIN AIR VENT FOR DOWN FLOW SYSTEMS OR DIAPHRAGM TYPE EXPANSION TANK Before system is filled with water there is air in pipes and radiation units Some of it will be trapped as system is filled It is possible to eliminate most of this air through air vent on radiation units Main air vent will...

Страница 26: ...l switch must be reset manually after switch has cooled off by pushing reset button down Check venting system and chimney for blockage when restoring system to operating condition DO NOT operate boiler without spill switch 17 EQUIPMENT AND OPTIONAL ACCESSORIES ROLLOUT SWITCH FLAME ROLLOUT SAFETY SHUTOFF Rollout switch is temperature sensitive fuse link device Located on boiler base just outside fi...

Страница 27: ... Check sensing bulb is fully inserted in well and is not loose Refer to enclosed addendum for wiring instructions when using indirect hot water heater A 3 Adjusting Settings To discourage unauthorized changing of settings pro cedure to enter adjustment mode is required To enter adjustment mode press UP DOWN and I buttons simultaneously for three seconds Press and release I button until parameter r...

Страница 28: ...ore retry Flame signal was lost during state 7 or 8 and delay is called before retry 32 second delay 13 Soft lock out Soft lockout duration is one hour may override with manual reset 14 Hard lock out Manual reset is required for hard lockout 15 Wait for limit to close Possible thermostat call for heat limit switch is open 16 Flame out of sequence Flame signal sensed before trial for ignition Appro...

Страница 29: ...and display On retry models wait for retry or reset at thermostat Check for correct installation and wiring before replacing any component Control module cannot be repaired If it malfunctions it must be replaced Use only qualified service agent to service ignition systems Perform checkout as first step in troubleshooting 1 Check troubleshooting guide to pinpoint cause of problem See Table 7 page 3...

Страница 30: ...lockout is reset after one hour if alarm reason disappears 63 Soft lockout maximum number of recycles exceeded Soft lockout 64 Soft Lockout electronics failure On board self diagnostics detected error Soft lockout 65 Over temperature error Sensor measured temperature in excess of maximum allowable limit Soft lockout Note Soft lockout time is 1 hour or manual reset Hard lockout requires manual rese...

Страница 31: ... damaged wire Check for cracked ceramic insulator which can cause short to ground and replace igniter sensor if necessary At gas valve disconnect main valve wire from MV terminal Turn on power and set thermostat to call for heat Pilot should light main burner will remain off because main valve actuator is disconnected Check pilot flame Verify it is blue steady and envelops 3 8 to 1 2 in 10 to 13 m...

Страница 32: ...COLUMBIA BOILER COMPANY Main offices and factory Pittstown PA ...