Instruction Booklet IB

Effective January 2017

XAP Series Busduct

Storage, Installation, and Maintenance

 DANGER

HAZARD OF ELECTRICAL SHOCK OR BURN. TURN THE POWER TO THE 
BUSDUCT OFF BEFORE INSTALLING, REMOVING, OR WORKING ON THIS 
EQUIPMENT.

 WARNING

LIVE EQUIPMENT MAY LEAD TO PHYSICAL HARM. UNLESS OTHERWISE 
STATED, THE EQUIPMENT MUST BE POWEROFF BEFORE INSTALLING, 
INSPECTION AND MAINTAINS.

 WARNING

DAMP BUSDUCT MUST BE TREATED PROPERLY. AND THE INSULATION 
RESISTANCE MUST BE TESTED POSITVELY BEFORE INSTALLATION.

Introduction

This publication contains instructions for the storage, handling, 

installation, and maintenance of the Eaton XAP busduct. Only those 

qualified and trained in accordance with established safety procedures 

should handle, install, and maintain the XAP busduct. Failure to follow 

danger, warning labels and established safety procedures could result 

in property damage, serious personal injury, or death.

This publication does not cover all the details or variation in equipment 

and hardware nor cover every possible contingency regarding storage, 

handling, installation, and maintenance for XAP busduct systems. 

Eaton does not make representation or warranty, expressed or implied 

and does not assume responsibility for the accuracy or completeness 

of information contained herein.

Receiving

Once the material is received, inspect each box/crate for damage. Also 

check for concealed damage. Should any damage be found, notify the 

carrier immediately and file any claims as required by the carrier. If no 

visible or concealed damage is found, the product is ready for storage 

or installation.

Do not remove the busduct from the original shipping container until 

ready for installation. This will help prevent damage to the busduct 

from occurring prior to installation.

Unloading and Handling

Suitable device should be used to unload the busduct to avoid damage. 

Forklift is recommended to use.

When lifting or hoisting the busduct, make sure the weight of the 

busduct is distributed and balanced. Use lifting devices that will not 

damage the busduct. Terminals of busduct cannot be used to support 

the weight of busduct. 

Storage

The Eaton XAP busduct should be stored in a covered, clean, dry space 

which is climate controlled to prevent condensation. Do not allow the 

busduct to come in contact with corrosive fumes, liquids, salts, or 

forms of concrete.

Storing the busduct outdoors should be avoided at all possible. 

However, if it cannot be avoided, it must be stored off the ground and 

securely covered to provide protection from dirt and moisture. 

Temporary electrical heating must be provided and evenly distributed 

beneath the cover to prevent condensation. At least 3 watts per cubic 

foot is adequate for average environments. Failure to properly store 

and protect the busduct may cause damage and will void the warranty.

Outdoor-rated busducts are not rated for outdoor applications until they 

are completely and properly installed. They should be treated as indoor 

busducts prior to complete installation.

Preparation and Inspection

Qualification and Training 

Only qualified professionals should install, operate and maintain the 

XAP busduct. Professionals should:

1. Fully understand the structure, installation, operation of XAP as well 

as the danger during operation;

2. Well trained about charging and test of the equipment;

3. Equipped with PPE such as safety helmet, working cloths.

Instrument and tool

The following instruments and tools will be used during installation:

1. Insulation tester 1000V;

2. 8-10, 10-12 wrench, sleeve and torque wrench;

3. Straight and cross screwdriver;

4. Gradienter, tape and filament;

5. Scaffold, hoist and herringbone ladder;

6. Drill, cutting machine, welding machine etc.

Inspection

Deliver all busduct sections and components to the installation location 

prior to unpacking, if possible. This will help prevent damage. Each 

crate/box is clearly marked with its contents and quantities.

Unpack and inspect each piece for any signs of visible damage. Check 

the housing for dents or cracks caused by physical damage. Inspect 

the XAP busduct joints to ensure they are clean and that the insulators 

are not cracked or broken. 

Consult the factory regarding any physical damage.

Perform an insulation resistance test on each busduct section by 

Megger testing at 1000 volts, phase-to-phase, phase-to-neutral, and 

phase-to-ground 

20M

Ω

 to ensure system integrity.

Record the readings of each item and of each installed run. Provide 

these readings as part of the permanent maintenance records.

Once inspected and tested, each busduct section is ready for installa-

tion.

Содержание XAP Series

Страница 1: ...xpansion Joint Installation End Cover Installation Settlement Joint Installation Horizontal Mounting Vertical Mounting Wall Penetrations Busduct Joint Clearances Tap off Unit Installation Attentions f...

Страница 2: ...tored in a covered clean dry space which is climate controlled to prevent condensation Do not allow the busduct to come in contact with corrosive fumes liquids salts or forms of concrete Storing the b...

Страница 3: ...ion When connecting pieces of the Eaton XAP busduct together make certain that contact surfaces are clean and free from contaminants Some section may have electrical lubricant on the contact surfaces...

Страница 4: ...the installation drawing Notes after completion of one line installation it is necessary to loosen all M6 25 bolts in the expansion joints to ensure expansion effect see Figure 7 Figure 7 Expansion J...

Страница 5: ...dened at the joints 3 Care should be given when locating drop rods in order to avoid placing hangers at joint and tap off unit locations Adequate ceiling clearance must be allowed for tap off units Ve...

Страница 6: ...able to avoid movement 2 Tap off unit shall not be burdened with load directly Loads at the rear end shall be fastened onto the busduct or other fixed positions in accordance with regulations 3 When n...

Страница 7: ...st be kept clean during installation 2 Busducts must be adjusted and kept in the same line before fastening the bolts of joint units Tolerance of assembly in horizon and vertical direction are 5mm per...

Страница 8: ...the mechanisms of all electrical and mechanical interlocks and padlocking means 8 Check for missing or broken parts rusting corrosion dirt and excessive wear 9 Check the line and load connections to e...

Страница 9: ...the environment through the use of power management technologies and services Eaton has approximately 95 000 employees and sells products to customers in more than 175 countries For more information...

Отзывы: