Eaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual
S
P-164000500 Rev 4
www.eaton.com/powerquality
3-1
Chapter 3
UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the UPS system (Chapter 3).
2.
Prepare your site for the UPS system (Chapter 3).
3.
Inspect and unpack the UPS sections (Chapter 3).
4.
Unload and install the UPS sections, and wire the system (Chapter 4).
5.
Install features, accessories, or options, as applicable (Chapter 5).
6.
Complete the Installation Checklist (Chapter 4).
7.
Have authorized service personnel perform preliminary operational checks and
start up the system.
NOTE
Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page W-1 become void. This service is offered as part of the
sales contract for the UPS. Contact an Eaton service representative in advance (usually a two-week notice is
required) to reserve a preferred startup date.
3.1
Creating an Installation Plan
Before installing the UPS system, read and understand how this manual applies to the
system being installed. Use the procedures and illustrations in paragraph 3.2 and
Chapter 4 to create a logical plan for installing the system.
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet
the environmental parameters outlined in this manual. If the UPS is to be operated at
an altitude higher than 1000m (3300 ft), contact an Eaton service representative for
important information about high altitude operation. The operating environment must
meet the weight, clearance, and environmental requirements specified.
3.2.1
Environmental Considerations
Make sure that the environment for the Eaton 9395P-1200 UPS meets the following
operating restrictions:
The environmental requirements specified below are for the air at the intake ports of
the Eaton 9395P-1200, and are the maximum, not to exceed, ratings.
S
There shall be at least a 1.0°C (1.8°F) difference between the dry bulb
temperature and the wet bulb temperature, at all times, to maintain a
non-condensing environment.
S
The maximum rate of temperature change shall be limited to 3°F over 5 minutes
(36°F/hour), based on the ASHRAE Standard 90.1-2013.
Figure