Installation Guide

GREEN MOTION FLEET & BUILDING

   www.eaton.com

Construct the pedestal mount conduit assembly 
by pressing the 1” trade size conduit (3” length)

 

(1)

 into the 1-inch trade size 90-degree conduit 

fitting 

(2)

 .

Place an o-ring 

(3) 

on the 90-degree fitting 

(2)

Slide the pedestal mount conduit assembly 

(4)

 

onto the lineside conductors 

(5)

 and up into  

the EV charger 

(6)

, where it press-fits .

Feed the lineside conductors 

(1)

 

through the opening in the pedestal 
and through the 1" conduit locknut 

(2)

 .

Insert the conduit assembly 

(3)

  

into the pedestal and connect the 
locknut 

(2)

 to it .

STEP C-5

STEP C-6

Reference:
1

.

 

1” trade size conduit

2

.

 

90° conduit fitting

3

.

 

O-ring

4

.

 

Conduit assembly

5

.

 

Lineside conductors

6

.

 

EV charger

Reference:
1

.

 

Lineside conductors

2

.

 

1” conduit locknut

3

.

 

Conduit assembly

1

2

3

4

6

1

3

2

5

Содержание Green Motion Fleet

Страница 1: ...Installation guide Green Motion Fleet Green Motion Building Green Motion chargers...

Страница 2: ...ALLATION Safety information 3 General reference 4 A Preparing the EV charger s 5 B Mount an EV charger to a wall 6 C Mount an EV charger to a pedestal 9 D Mount a second EV charger to a pedestal 15 FC...

Страница 3: ...Green Motion chargers AC Level 2 deliver fast and cost effective charging for passenger vehicles and medium duty trucks used for last mile delivery Combining breakout capabilities for metering control...

Страница 4: ...ehicle connected EVSE ready Long Blue Short Blue No Blink Blue Long Red Vehicle charging state EVSE not ready 1 Charging Fault 2 No Blink Green Medium Blue Vehicle connected Idle Ready READY CHARGE FA...

Страница 5: ...G IN ELECTRIC VEHICLES ONLY PREMISE VENTILATION NOT REQUIRED THIS DEVICE SHOULD BE SUPERVISED WHEN USED AROUND CHILDREN WARNING TURN OFF OR DISCONNECT THE POWER SUPPLYING THIS EQUIPMENT BEFORE BEGINNI...

Страница 6: ...and not more than 4 ft 1 2 m above the floor level for indoor loca tions and 24 inches 600 mm above the grade level for outdoor locations WARNING Risk of Explosion This equipment has arcing or sparkin...

Страница 7: ...ar of the charger and then remove the front cover 2 Unscrew the two bolts 1 on the side of the adapter plate and remove the plate 2 Set the bolts aside for now If a SIM card is not needed then skip th...

Страница 8: ...Section C Reference 1 Adapter plate 2 M6 screws x4 3 Anchor x4 Reference 1 EV charger 2 Adapter plate 3 Bolts x2 B Mount an EV charger to a wall Use the adapter plate 1 as a template mark the hole pat...

Страница 9: ...to the junction box and connect inside the junction box Suggest using the Polaris lugs provided in the kit for wiring inside the junction box Secure the cover of the junction box 4 STEP B 5 1 4 3 2 F...

Страница 10: ...tor assembly 2 STEP B 7 Reference 1 1 2 trade size conduit 2 Connector assembly 3 Ethernet port 4 EV charger Optional Assemble the custom Ethernet adapter connector 1 the 1 2 o ring 2 and the 1 2 NPT...

Страница 11: ...ments Reconnect power to the upstream circuit by switching circuit breaker to the ON position Energize the loadcenter or the panelboard The EV charger electronics should power immediately and the LCD...

Страница 12: ...e with the EV pedestal With that hardware install the premium cord holster 3 onto the pedestal using 1 4 20 hex head bolts washers and serrated flange nuts 4 Install the adapter plate 5 onto the front...

Страница 13: ...embly 4 onto the lineside conductors 5 and up into the EV charger 6 where it press fits Feed the lineside conductors 1 through the opening in the pedestal and through the 1 conduit locknut 2 Insert th...

Страница 14: ...e conduit 5 into the assembly 6 STEP C 8 Reference 1 Ethernet cable 2 1 2 plastic nut 3 Small opening in EV pedestal 4 1 2 NPT 90 degree adapter 5 10 5 conduit 6 Connector assembly 7 Ethernet port Opt...

Страница 15: ...ired lengths and connect them with their respective power cables using two Polaris lugs 1 Install a ring terminal on the EV charger ground conductor and connect it to the pedestal ground stud 1 Secure...

Страница 16: ...stal then skip to Section D Reconnect power to the upstream circuit by switching circuit breaker to the ON position Energize the loadcenter or the panelboard The EV charger electronics should power im...

Страница 17: ...to the pedestal 2 using the ten speed screws 3 Install the last bolt washer and nut 4 to the plate assembly Repeat Steps C 3 through C 11 to mount the second EV charger STEP D 1 STEP D 2 Reference 1 B...

Страница 18: ...le access panel 3 1 4 20 hex head bolts 1 4 washers 1 4 20 locknuts 4 Mid panel assembly 5 Lower access panel 6 EV pedestal 7 10 speed screws STEP D 4 STEP D 5 Reconnect power to the upstream circuit...

Страница 19: ...ourself If the unit requires servicing please contact Eaton customer service The installation maintenance and servicing of your EV charger must only be performed by qualified personnel in accordance w...

Страница 20: ...material for three 3 year from the date of original purchase In the event any Product fails to comply with the foregoing warranty Seller will at its option either a repair or replace the defective Pro...

Страница 21: ...he EV charger will timeout and authentication failed messgae is displayed Contact a certified electrician to make sure the RFID module is not disconnected from the main EV charger electronics Why is t...

Страница 22: ...trademark All trademarks are property of their respective owners Eaton 1000 Eaton Boulevard Cleveland OH 44122 United States Eaton com 2022 Eaton All Rights Reserved Printed in USA Publication No IL1...

Отзывы: