Instruction Booklet 

IB0191002EN

Effective November 2019

EAFR-101C arc point sensor relay  

user manual 

  

EATON

 www.eaton.com

Figure 8. EAFR-101C cut out for panel mounting (mm [in.]).

47 (1.85)

23.5        (0.93)

159 (6.26)

168 (6.61)

M4

9 Testing

It is recommended that the EAFR-101C relay be tested prior to 

substation energizing .  Testing is carried out by simulating arc light 

to each sensor and verifying the tripping and LED indication .  For 

arc light simulation, a suitable light source is provided as part of 

the Eaton AQS Tester kit .  If an AQS Tester is not present, a camera 

flash can be used .  A Canon Speedlite

®

 430EX or equivalent works 

well .  Check that the light source has fully charged battery(ies) when 

testing .

9.1 Carrying out testing in the light only mode

1 . 

Check that the dipswitch setting positions are in accordance 

to your application.

2 . 

Activate the light source close to the EAFR-01 to be used.

3 . 

Verify that the corresponding sensor channel indication LED 

status is changed to ON.

4 . 

Verify the relay output(s) activation(s) by checking the 

circuit breaker status or by monitoring trip contact status.  

If a circuit breaker is connected to a trip output, the circuit 

breaker should open or contacts operate.

ote: 

N

A best practice is to operate the circuit breaker during testing .

5 . 

Verify that the corresponding relay output(s) LED(s) indica-

tion status is changed to ON.

6 . 

If the binary output (BO1) signal is utilized, verify the BO1 

signal activation by the status change of the relevant input 

where the binary output signal is connected, or by measur-

ing the signal output voltage.

ote: 

N

The BO1 signal is a non-latched type .

7 . 

If a binary output signal is utilized, verify that the BO1 LED is 

illuminated.

8 . 

Press the SET push-button to reset all indications and 

latches.

9.2 Carrying out testing in light and current mode

1 . 

Check that the dipswitch setting positions are in accordance 

with your application.

2 . 

Activate the light source close to the EAFR-01 to be used and 

simultaneously activate the binary input BI5 used for over-

current condition.  BI5 activation may be done by supplying 

current to a connected EAFR-110PLV (see AQS Tester Manual 

IB019011EN).

3 . 

Verify that the sensor channel indication LED status is 

changed to ON.

4 . 

Verify that the binary input indication LED status is changed 

to ON.

5 . 

Verify the relay output(s) activation(s) by checking the circuit 

breaker status or by monitoring trip contact status.

ote: 

N

A best practice is to operate circuit breaker at testing .  The circuit 

breaker should open or the contacts should operate .

6 . 

Verify that the corresponding relay output(s) LED(s) indica-

tion status is changed to ON.

7 . 

If a binary output (BO1 and BO2) signals are utilized, verify 

the BO signal activation by status change of relevant input 

where binary output signal is connected, or by measuring 

the signal output voltage.

8 . 

Verify that the corresponding relay output(s) LED(s) indica-

tion status is changed to ON

9 . 

Press the SET push-button to reset all indications and 

latches.

Содержание EAFR-101C

Страница 1: ...on 2 2 General 2 3 Operation and configuration 4 4 Arc sensors 7 5 System self supervision 8 6 Application examples 9 7 Connections 9 8 Dimensions and installation 11 9 Testing 12 10 Troubleshooting g...

Страница 2: ...m the point sensor and acting to trip the circuit breaker sourcing the fault current The EAFR 101C complete system self supervision function provides the highest level of dependability by continuously...

Страница 3: ...7 6 13 BI2 X2 12 15 BI1 14 LATCH EN SW6 11 T1 10 LATCH EN SW6 9 T2 8 SF 5 4 3 2 Uaux 1 125 250 Vdc 24 Vdc 24 Vdc 110 220 Vac dc 24 Vdc 12 Vdc 12 Vdc 5 Vdc uP 12 BI4 11 15 BI3 14 10 BI5 9 8 BI6 7 6 BO1...

Страница 4: ...al Verify system condition See Sections 11 Troubleshooting guide and 5 System self supervision T1 and T3 Red Normal status Trip relays T1 and T3 activated N A Check the reason for trip Clear the fault...

Страница 5: ...indications and latched trip relays are reset by pressing the SET button for one second Otherwise the latched trip relays will remain activated until auxiliary power is disconnected All LED indi cati...

Страница 6: ...channel S3 S4 trip criteria Trip on light only L Trip on light and over current L C Both signals are required simultaneously to trip 6 Latch or non latch for trip relays T1 and T2 T1 and T2 operate as...

Страница 7: ...rees Other point sensors are available with different Lux sensitivities EAFR 01 B at 25 000 Lux and EAFR 01 C at 50 000 Lux Figure 4 EAFR 01 arc light point sensor 4 1 1 EAFR 01 installation and wirin...

Страница 8: ...ealthy condition the POWER LED is on and the System Failure SF relay is energized If the self supervision function detects a faulty condition or the power supply fails the self supervision relay is re...

Страница 9: ...ow voltage switchgear 7 Connections Figure 6 EAFR 101C terminals at the rear plate 7 1 Outputs 7 1 1Trip relaysT1 T2 andT3 The EAFR 101C relay has integrated trip relays T1 and T2 for tripping of the...

Страница 10: ...opening operation before the primary contacts part these outputs can be connected to BI1 BI2 or BI3 BI4 If an input is received on either of these two input pairs the EAFR 101C restrains sending any l...

Страница 11: ...ser manual EATON www eaton com 8 Dimensions and installation The EAFR 101C is either door mounted or panel mounted in stan dard 19 in 482 6 mm rack height of 4U and 1 8 of a unit wide Figure 7 EAFR 10...

Страница 12: ...al is utilized verify the BO1 signal activation by the status change of the relevant input where the binary output signal is connected or by measur ing the signal output voltage ote N The BO1 signal i...

Страница 13: ...ns Light only Light current Remarks Sensor channels 1 and 2 setting Sensor channels 3 and 4 setting Object activated LED indication T1 T2 and T3 active BO1 active BO2 active Sensor channel 1 Sensor 1...

Страница 14: ...y for 0 5 s 30 A Make and carry for 3 s 16 A Breaking capacity DC when time constant L R 40 ms 40 W 0 36 A at 110 Vdc Contact material AgNi 90 10 11 4 Binary output BO1 and BO2 Rated voltage 24 Vdc Ra...

Страница 15: ...ulse test voltage Acc to IEC 60255 5 5 kV 1 2 50 us 0 5 J 11 8 Mechanical tests Vibration test 10 to 150 Hz 0 07 mm 003 in 0 5 gn 60 to 150 Hz 10 to 150 Hz 1 gn 10 to 150 Hz Shock bump test acc to IEC...

Страница 16: ...fiber sensor 30 m 93 43 ft EAFR 06 35 65C2013G06 Arc light plastic fiber sensor 35 m 114 83 ft EAFR 06 40 65C2013G07 Arc light plastic fiber sensor 40 m 131 23 ft EAFR 07 10 65C2014G01 Arc light glass...

Страница 17: ...17 Instruction Booklet IB0191002EN Effective November 2019 EAFR 101C arc point sensor relay user manual EATON www eaton com Notes...

Страница 18: ...t between Eaton and the purchaser THERE ARE NO UNDERSTANDINGS AGREEMENTS WARRANTIES EXPRESSED OR IMPLIED INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY OTHER THAN THOSE SP...