Access Power Solutions Installation Guide (APS6-400 Series)
36
Copyright © 2009-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-53B December 2010
Start-Up Tasks
Complete all the Installation tasks (see details on page
) before starting these Start-Up tasks.
Complete the Start-Up tasks in the following order:
Task Description
Reference
1
Insert the Rectifiers
See details on page
2
Complete the Pre-Power-Up Checklist
See details on page
3
Apply AC Power
See details on page
4
Configure the dc power system
See details on page
5
Apply DC Power to Battery and Load
See details on page
Task 1 - Inserting the Rectifiers
Do NOT install the rectifiers until the room has been cleaned and is dust free.
Do NOT switch on the ac supply at this stage.
Step 1 - Unpack the rectifiers
Unpack the rectifiers and inspect them carefully for possible transport damage.
Report any damage immediately using a completed Equipment Incident Report on
page
Keep the original packaging to return a rectifier for replacement or repair, if required.
Step 2 - Fit first rectifier
1
Align the rectifier with the left side of the shelf.
2
Push in the rectifier until the retaining screw contacts the shelf.
3
Check the rectifier's rear connector is correctly aligned with the shelf connector,
or damage may occur.
4
Tighten the retaining screw to 1.5Nm (13.3 inch-pounds). This will locate the
rectifier in its rear connector.