![Eaton APS6-400 Series Скачать руководство пользователя страница 37](http://html1.mh-extra.com/html/eaton/aps6-400-series/aps6-400-series_installation-and-operation-manual_3770729037.webp)
Installation
Copyright © 2009-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-53B December 2010
29
Battery CB
Cable
size
(Note 1)
2-hole or 3-hole Crimp Lug
(¼" studs, 5/8" spacing)
(Note 2)
Crimping tool
(Note 2)
80A
2 AWG
YA2CL-2TC14
Y1MR
100A
1 AWG
YA1CL-2TC14
120A
1 AWG
YA1CL-2TC14
150A
1/0 AWG
YAV25L-2TC
Y81KFT,
Y81KFTMBH,
PAT81KFT18V
175A
2/0 AWG
YAV26L-2TC
200A
3/0 AWG
(Note 3)
YAV25L-2TC
Notes:
1
Minimum cable size. Does not allow for excessive voltage drop in long cable runs at high
current.
2
Part numbers are for FCI-BURNDY® products. In US/Canada use these parts or equivalent
UL-listed crimp lugs.
3
If 3/0 AWG cable is not available, use 2/0 AWG cable and appropriate UL-Listed Crimp
Lug.
Step 2 - Connect load cables
1
Select load cable to suit the load circuit breaker (refer to following table).
2
Route the load cables to the APS.
3
Terminate the load live and common cable(s) with suitable crimp lugs (refer to
the following table).
4
Connect the load common cable(s) on the common bar at the load termination
points.
5
Terminate the load live cable(s) at the load circuit breaker terminal(s).
6
Tighten all terminations to 3.9 - 4.5Nm (35 - 39 inch-pounds).
7
Secure the cables to the tie bar.