36
30-200 kW
P-164000249
User's and Installation Guide
Revision 2
4 UPS system installation
The customer has to supply the wiring to connect the UPS to the local power source. The electrical
installation procedure is described in the following section. The installation inspection and the initial
start-up of the UPS and installing an extra battery cabinet must be carried out by qualified service
personnel such as a licensed service engineer from the manufacturer or from an agent authorized by
the manufacturer.
WARNING
Physical injury or death may follow, or damage may occur to the UPS or the load equipment if
these instructions are ignored.
4.1 Steps to install the UPS
Power and control wiring can be routed through the rear, bottom, or top of the cabinet, depending
on the model of the cabinet, with connections made to easily accessible terminals, see
Figure 4-1:
93PM 30-50 kW gland plate and connector locations
on page 37,
Figure 4-2: 93PM 80-150 kW
UPS gland plate and connector locations
on page 38,
Figure 4-3: 93PM 160-200 kW UPS gland
plate and connector locations
on page 39, and
Figure 4-4: 93PM 30-150 kW Top cable access kit
on page 40.
1.
If not already open, unfasten front door latch and swing door open.
2.
If the internal Maintenance Bypass Switch (MBS) is included, remove the screws securing the
MBS protection cover on bottom left of front panel. Then remove the Maintenance Bypass
Switch knob by loosening the screw in the middle of knob and pulling the knob off of the shaft.
3.
Remove the screws securing the safety shield panel in front of the connectors to gain access to
terminal blocks.
4.
Remove screws securing the rear wire entry plate to gain access through back wire entry way. If
the cables are to be installed with top-access kit, is not necessary to remove the rear plate.
5.
If installing power wiring from the bottom of the cabinet, proceed to step 6; rear access,
proceed to step 8. If installing the power wiring from top, proceed to step 7.
6.
Remove screws securing bottom wire entry plate.
7.
Remove the right side plate for cable installation access. Remove the needed cable gland plates
from the top of the top access cabinet.
8.
Drill or punch holes for the cable glands on the plate used for cable entry. Work must be
performed while the plate is outside the UPS cabinet to prevent metal shavings or chips from
entering on or into electronics.
9.
Install suitable cable glands on the plate.
10.
Route all the cables through wire way to the UPS terminal blocks.
11.
Reinstall wire entry plate and install conduit if needed.
12.
Route and connect power wiring.
Содержание 93PM IBC-L
Страница 1: ...Eaton 93PM UPS P 164000249 30 200 kW User s and Installation Guide...
Страница 2: ......
Страница 3: ...Eaton 93PM UPS 30 200 kW User s and Installation Guide...
Страница 19: ...P 164000249 30 200 kW 11 Revision 2 User s and Installation Guide Figure 2 2 93PM 50 kW UPS wiring diagram...
Страница 50: ...42 30 200 kW P 164000249 User s and Installation Guide Revision 2 Figure 4 5 93PM battery cabinet EBC S...
Страница 51: ...P 164000249 30 200 kW 43 Revision 2 User s and Installation Guide Figure 4 6 93PM battery cabinet EBC L...