74
Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for the
first time.
Distributed Bypass Installation Checklist
o
Each cabinet in the distributed bypass system is placed in its installed location.
o
All conduits and cables are properly routed to the UPS cabinets and to the tie cabinet or distribution panel.
o
All power cables are properly sized and terminated.
o
A ground conductor is properly installed.
o
Controller Area Network (CAN) wiring between the UPS cabinets is properly installed.
o
Pull-chain wiring between the UPS cabinets is properly installed.
o
Adequate workspace exists around the UPS cabinets, the tie cabinet, and other cabinets.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
Содержание 9395XC
Страница 8: ......
Страница 16: ...xvi Eaton 9395XC UPS 1200kW 1200kVA 1350kW 1350kVA or 1500kW 1500kVA 164001079 Rev 01 List of Figures ...
Страница 18: ...xviii Eaton 9395XC UPS 1200kW 1200kVA 1350kW 1350kVA or 1500kW 1500kVA 164001079 Rev 01 List of Tables ...
Страница 26: ...8 Eaton 9395XC UPS 1200kW 1200kVA 1350kW 1350kVA or 1500kW 1500kVA 164001079 Rev 01 Introduction ...
Страница 118: ...100 Eaton 9395XC UPS 1200kW 1200kVA 1350kW 1350kVA or 1500kW 1500kVA 164001079 Rev 01 Understanding UPS Operation ...
Страница 160: ...16400107901 164001079 01 ...