27
Eastman
Over a Century of Cutting Expertise
®
Form E-564
1. Turn the Power off to the Raptor, use
lockout/tagout if required
2. The Drive belt is located on the operator side
of the take off conveyor. Begin by Removing
(4) Flanged Screws.
3.
Remove Side Cover and disconnect the
three connectors.
4. Remove the Position Lock Screw and Lock
Washer as shown.
Take-Off Drive Conveyor
Belt Replacement
Flanged
Screw
Side Cover
Connectors
Position Lock
Screw
Lock
Washer
5. Loosen (4) mounting Screws as shown.
6.
Slide the Take-Off Conveyor Drive pulley
to the left to release the tension on the belt.
7. Remove the Belt and discard.
8. Reassemble in reverse order.
9. Tension the belt so the deflection is 1/8" or
3mm.
Mounting
Screws
Take-Off
Conveyor Drive
Pulley
Belt
67-27103