Isokern Maximus Linear Series See-Thru Gas Fireplace
19
Isokern Maximus Linear See-Thru Installation
2)
Set the first course of the firebox side walls and back walls into place
(Figure 9)
.
NOTE
: It may be convenient to dry set the first course of side walls in place atop the Isokern base plate and trace their
position onto the base plate. After outlining the dry set pieces, remove them and apply Earthcore Adhesive to the areas
traced on the base plate where the side walls are to sit. By doing this, the first layer of wall components can be set directly
into Earthcore Adhesive already applied to the proper areas on the base plate.
3)
Continue assembly of the consecutive courses of the firebox side walls. Apply Earthcore Adhesive to the top of each
layer of side wall components before setting the next course in place
(Figure 10)
. Look for some Earthcore Adhesive to
squeeze out along the joints of all contact surfaces as a sign that the joint is thoroughly sealed with the approved
Earthcore Adhesive.
4)
When all the firebox side wall components are set, check the top surface of the firebox for level. If necessary, adjust the
top surface of the box assembly for level by inserting a shim supplied with the unit between the lowest wall component
and the top surface of the base plate. Any gap created under the wall components during the shim leveling process
must be filled with Earthcore Adhesive.
Sidewall:
M65A
FIGURE 9
Sidewall:
M65A
FIGURE 10