028.01 Securing the Shelter
1.
Invert the Shelter so the white side is up.
2.
Spread the Shelter approximately one foot.
3.
Carefully push the interior liner between the struts so that all looped
keepers are exposed.
4.
Secure one of the cinch straps around the top section of the collapsed
shelter approximately 1.5 feet down from the top interior hubs as
shown in Figure 3-5.
Figure 3-5 - Secure First Cinch Strap
5.
Invert the Shelter so that the exterior cover is facing up.
6.
Compress and secure with a second cinch belt approximately 1.5 feet
from the exterior keepers as shown in Figure 3-6.
7.
Remove the compressed Shelter from the ground cover.
8.
Lay the Shelter on its widest side
9.
Lift the Shelter off the ground by the cinch straps or by the hubs
closest to the ground. Remember to lift with your legs, and not with
your back.
Figure 3-6 - Shelter Secured with Two Cinch Straps
029.01 Secure the Floor & Ground Cover
1.
Remove all ground stakes from the ground cover.
2.
Fold the Ground Cover into quarters lengthwise.
3.
Lay the folded Floor on top of the folded Ground Cover.
4.
Place the Shelter on its side at the end of the folded ground cover
and floor.
5.
Three people are required to wrap the ground cover and floor
around the Shelter.
a)
Have two people roll the Shelter.
b)
Have the third person tuck in the ground cover and floor as it
is wrapped around the Shelter (tucking the ground cover and
floor keeps the wrap tight and further compresses the Shelter).
Figure 3-7 - Rolling Shelter with Ground Cover
6.
When complete, stand the Shelter with the white side up, holding the Ground Cover close to the Shelter.
7.
Secure the Shelter with the third cinch belt in the center.
8.
Remove the Push Poles and Repair Kit from Transport Bag.
9.
Place the Transport Bag over the Shelter.
10.
Align the carrying straps on the outside of the bag with the end walls. This will allow the Instruction Panels to fall
against the wide section when slipped over the Shelter.
11.
Push the Shelter over with the instruction panel down.
12.
Return the Push Poles and Repair Kit to the Transport Bag.
13.
Pull the rope to close the end of the Transport Bag and secure bag with a knot.
14.
Fasten the two belts on the Transport Bag.
15.
The Shelter is now secure and ready for the next deployment.