ERECTING THE SHELTER
This manual and a separate video tape or CD-ROM has been prepared to assist you in understanding the correct procedure
for deploying and striking the Shelter.
WP M --- . -- -95310-02
Deployment Procedure
Whether the Shelter is to be used in a stand alone (single shelter) application or in a complex configuration (two or more
shelters interconnected), the set-up and take-down procedures are the same. THESE PROCEDURES MUST BE
FOLLOWED TO INSURE PROPER DEPLOYMENT AND STRIKING OF THE SHELTERS. Failure to follow these
simple procedures may hinder optimum performance or result in damage to the shelter.
001.01 Offloading the Shelter
To off-load the Shelter package from any platform;
1.
Assign one member from the four people (minimum) as the
TEAM LEADER to be responsible for coordinating the
smooth and uniform motion of the deployment crew.
2.
Lift and slide the shelter so that it remains parallel with the
ground (see Figure 2-1).
3.
Do not rock the shelter when off-loading. Rocking may
cause damage to the struts (see Figure 2-1).
YES YES
NO
Figure 2-1 - Offloading the Shelter
002.01 Position the Shelter
1.
Clear enough space to erect the Shelter.
2.
Open the Transport Bag and remove the Field Repair Kit, Push Poles, and cinched Shelter.
3.
Unwrap the Ground Cover and Floor. The Ground Cover has coated staking loops around the edge.
4.
Identify and remove the floor from the immediate area for later use.
5.
Place the ground cover on site (Stenciled side up) and stake down. The stakes
MUST
be flush to the ground.
6.
Place the Shelter on the center of the ground cover with the
exterior side facing up and the white side down.
7.
Orient the long side of the Shelter with the long side of the
ground cover. Proper alignment will reduce the possibility
of having to reposition the Shelter later.
8.
Remove the Shelter cinch straps and place them in the
Transport Bag to prevent loss. The Repair Kit should also
be returned to Transport Bag.
Figure 2-2 - Position the Shelter on the Ground Cover
CAUTION
THIS STEP REQUIRES FOUR PERSONNEL
TO LIFT THE SHELTER PACKAGE FROM
THE TRANSPORT VEHICLE AND LOWER IT
TO THE GROUND.