43
Operation and Installation Manual for SOLIVIA 10.0 / 11.0 EU G4 TR
8. Commissioning
EN
➔
Termination: On
Baudrate: 19200
ID: 1
continue
-------------------
RS485
16. Press the
buttons to select
continue
and then
press the button.
→ The completion screen will be displayed.
to reselect
ESC:
to confirm
ENTER:
17. Press the button to complete commissioning.
or
Press the
ESC
button to change settings.
þ
Commissioning is now fi nished.
nOTE
► If the solar power inverter is confi gured to the
DE LVD,
DK LVD
or
DE MVD
grids, you can also confi gure active and
reactive power control, see
“10.9 Active power control”, p. 56
and
“10.10 Reactive Power Control”, p. 58
.
► The solar power inverter offers some optional functions available for all grids, see
“10 Settings”, p. 52.
► On completion of commissioning, save the settings (see
“11.5 Saving settings”, p. 68
) and the swap data (see
“11.7 Saving swap data”, p. 70
) on a USB stick so that you can use this information later.
Содержание SOL10.0-1TR3-E4
Страница 1: ...Operation and Installation Manual for SOL10 0 1TR3 E4 SOL11 0 1TR3 E4...
Страница 89: ......