31
Operation and Installation Manual for SOLIVIA 10.0 / 11.0 EU G4 TR
8. Commissioning
EN
8.3
Selecting the Correct Commissioning Procedure
The solar power inverter must be newly installed:
Country
Grid (as shown
on display)
Description
Applicable Commissioning Procedure
Belgium
BE C10/11 12
Synergrid C10/11 2012
“8.4 Commissioning for grids as per EN 50438
and VDE 0126”, p. 32
Bulgaria
BG
VDE 0126-1-1
Denmark
DK LVD
VDE AR N 4105
“8.5 Commissioning for VDE AR N 4105
grids”, p. 35
Germany
DE LVD
VDE AR N 4105
DE MVD
BDEW
“8.6 Commissioning for grids as per BDEW”,
p. 38
France
FR ISL. 60Hz
French Islands 60 Hz
“8.4 Commissioning for grids as per EN 50438
and VDE 0126”, p. 32
FR UTE
UTE 15 712-1
FR VFR 2013
VFR 2013
FR VFR 2014
VFR 2014
Greece
GR CONTINENT
Greece/continental, VDE 0126-1-1
GR ISLAND
Greece/islands, VDE 0126-1-1
Netherlands
NL
VDE 0126-1-1 + EN 50438
Poland
PL
EN 50438
Portugal
PT
EN 50438
Romania
RO
VDE 0126-1-1
Slovakia
SK
VDE 0126-1-1
Spain
ES RD661
RD661
ES ISLAND
RD1663 Spanish islands
ES RD1699
RD1699
Czech Republic
CZ
VDE 0126-1-1 + EN 50438
United Kingdom
UK G59-2 230
G59-2 230 V
UK G59-2 240
G59-2 240 V
The solar power inverter must be set up with the same settings as another identical solar
power inverter.
“8.7 Commissioning by loading the settings
from another solar power inverter”, p. 41
The solar power inverter is a replacement device for another identical solar power inverter.
“8.8 Commissioning after replacing a solar
power inverter”, p. 44
The solar power inverter should be newly set up and the grid to which the solar power
inverter is connected is
not
shown in the list above.
You can set up a customer-specific grid.
Please contact Delta Support by phone.
Содержание SOL10.0-1TR3-E4
Страница 1: ...Operation and Installation Manual for SOL10 0 1TR3 E4 SOL11 0 1TR3 E4...
Страница 89: ......