Figure 13. Attach front rail adapter
9. Repeat the steps for the second rail.
10. After installing both rails, make sure that they are level with one another.
11. For HA systems, repeat this procedure for the second node.
Install the DD9800 system into a rack
About this task
CAUTION:
Data Domain systems are heavy. Always use two people or a mechanical lift to move a system. The
chassis displays warning signs.
Figure 14. Warning about lifting the system
CAUTION:
●
Do not apply AC power to the DD9800 system controller until all expansion shelves and cables are installed.
●
Make sure the PSNT label, attached to the left rear of the chassis is not damaged or snagged during the
installation of the system into the rack.
Install the System in the Rack
19
Содержание Data Domain DD9800
Страница 1: ...Dell EMC Data Domain DD9800 System Installation Guide September 2020 Rev 02 ...
Страница 65: ...Figure 66 DD9800 with ES30 shelves ERSO Connect Cables and Power On 65 ...
Страница 68: ...Figure 68 DD9800 with DS60 shelves DD9800 with HA For an HA DD9800 pair 68 Connect Cables and Power On ...
Страница 70: ...Figure 69 DD9800 with DS60 shelves HA 70 Connect Cables and Power On ...