Installation, operation and maintenance instructions - VMGFE102

13  STARTUP

13.1 - Preliminary checks

Never be tempted to start the heat pump without reading 
fully, and understanding, the operating instructions and 
without having carried out the following pre-start checks:
• 

Check the chilled water circulation pumps, air handling 
units and all other equipment connected to the evapo-
rator. 

• 

Refer to the manufacturer’s instructions.

• 

For units without hydronic module, the water pump 
overheat protection device must be connected in series 
with the pump contactor power supply. 

• 

Refer to the wiring diagram supplied with the unit.

• 

Ensure that there are no refrigerant leaks.

• Confi rm that all pipe securing bands are tight.
• Confi rm the the electrical connections are secure.

13.2 - Actual start-up

IMPORTANT:

• 

Commissioning and start-up of the heat pump must be 
supervised by a qualifi ed refrigeration engineer.

• 

Start-up and operating tests must be carried out with a 
thermal load applied and water circulating in the water heat 
exchanger.

• 

All set point adjustments and control tests must be carried 
out before the unit is started up.

• 

Please refer to the AR05 017-160 Control manual.

The unit should be started up in Local ON mode. Ensure that 
all safety devices are satisfi ed, especially the high pressure 
switches.

13.3 - Operation of two units in master/slave mode

The control of a master/slave assembly is in the entering 
water and does not require any additional sensors (standard 
confi guration). It can also be located in the leaving water. In 
this case two additional sensors must be added on the 
common piping.

All parameters, required for the master/slave function must be 
confi gured using the Service Confi guration menu. All remote 
controls of the master/slave assembly (start/stop, set point, 
load shedding, etc.) are controlled by the unit con-fi gured as 
master and must only be applied to the master unit.

Depending on the installation and control type, each unit can 
control its own water pump. If there is only one common 
pump for the two units, the master unit can control this. In 
this case shut-off  valves must be installed on each unit. They 
will be activated at the opening and closing by the control of 
each unit (and the valves will be controlled using the 
dedicated water pump outputs).

Standard confi guration: return water control

Confi guration: leaving water control

Legend

 Master 

unit

 Slave 

unit

 

Additional CCN board (one per unit, with connection via communication bus)

 

Control boxes of the master and slave units

 Water 

inlet

 Water 

outlet

 

Water pumps for each unit (included as standard for units with hydronic 
module)

 

Additional sensors for leaving water control, to be connected to channel 1 of 
the slave boards of each master and slave unit

 

CCN communication bus

 

Connection of two additional sensors

 Check 

valve

T

Содержание AR05 017 Series

Страница 1: ...t Pumps Nominal cooling capacity 40 150 kW Nominal heating capacity 40 160 kW 50 Hz For the operation of the control please refer to the Control manual for the AR05 017 160 series Installation operati...

Страница 2: ...wer supply 14 10 3 Voltage phase imbalance 14 10 4 Recommended wire sections 14 10 5 Field control wiring 15 10 6 Power supply 15 11 WATER CONNECTIONS 15 11 1 Operating precautions and recommendations...

Страница 3: ...Refrigerant 26 14 10 High pressure safety switch 26 14 11 Receiver 26 14 12 Four way valve 26 15 OPTIONS AND ACCESSORIES 27 14 13 Control box 27 16 STANDARD MAINTENANCE 28 16 1 Level 1 maintenance 28...

Страница 4: ...e declarations of conformity for these products 1 2 Check equipment received Inspect the unit for damage or missing parts If damage is detected or if shipment is incomplete immediately le a claim with...

Страница 5: ...hat ensures that people and property are not exposed to refrigerant leaks These uids may be di used in the air but far away from any building air intake or they must be discharged in a quantity that i...

Страница 6: ...that has leaked is generally lower than its original calibration The new calibration may a ect the operating range To avoid nuisance trippingorleaks replaceorre calibratethevalve OPERATING CHECKS IMPO...

Страница 7: ...is running Be sure pressure is at 0 kPa before removing components or opening a circuit Do not attempt to repair or recondition any safety devices when corrosion or build up of foreign material rust d...

Страница 8: ...refer to the chapter Dimensions and clearances to con rm that there is adequate space for all connections and serviceoperations Forthecentreofgravitycoordinates the position of the unit mounting holes...

Страница 9: ...the location of xing points weight distribution and coordinates of the centre of gravity refer to the certi ed dimensional drawings B In multiple unit installations maximum four units the side clearan...

Страница 10: ...of the centre of gravity refer to the certi ed dimensional drawings B In multiple unit installations maximum four units the side clearance between the units should be increased from 1000 to 2000 mm C...

Страница 11: ...hown is a guideline only To nd out the unit refrigerant charge please refer to the unit nameplate In accordance with ISO 9614 1 for information only The values have been rounded and are for informatio...

Страница 12: ...onsidered always contact your local Danfoss representative The required protection level for this class is IP43BW according to reference document IEC 60529 All AR05 units are protected to IP44CW and f...

Страница 13: ...o add a storage tank to the circuit This tank should be equipped with ba es to allow mixing of the uid water or brine Please refer to the examples below 9 2 Operating range standard units heating mode...

Страница 14: ...Pure water litres 600 400 200 1680 1120 560 10 ethylene glycol l 450 300 150 1260 840 420 20 ethylene glycol l 330 220 110 930 620 310 30 ethylene glycol l 270 180 90 750 500 250 40 ethylene glycol l...

Страница 15: ...replaced more frequently every 15000 operating hours instead of 25000 hours for an appliacation using water Recommendations on heat exchange uids No NH4 ammonium ions in the water they are very detrim...

Страница 16: ...hanger and internal piping that have an automatic supply and by pump cycling units with hydronic module and Reinforced frost protection option Never switch o the water heat exchanger and hydronic circ...

Страница 17: ...t leaving pressure information see installation manual Check valve Note x 2 for a dual pump not provided for a single pump Plate heat exchanger Water heat exchanger frost protection heater Installatio...

Страница 18: ...et and outlet item 19 As the total system pressure drop is not known exactly at the start up the water ow rate must be adjusted with the control valve to obtain the speci c ow rate for this system Hyd...

Страница 19: ...e connected to the unit inlet and outlet item 19 Let the pump run for two consecutive hours to clean the hydronic circuit of the system presence of solid contaminants Take another reading Compare this...

Страница 20: ...er is not contaminated Pressure di erential set point control procedure Once the circuit has been cleaned select the hydronic circuit con guration for which the unit selection has been made in general...

Страница 21: ...rate that the maximum value or a higher frequency than the maximum value the system settles at the maximum ow rate or maximum frequency and this results in a higher delta T value than the set point H...

Страница 22: ...05 120 160 Pressure drop kPa Pressure drop kPa Water ow rate l s Water ow rate l s Water ow rate l s Water ow rate l s Legend 1 AR05 039 2 AR05 045 3 AR05 050 4 AR05 060 5 AR05 070 6 AR05 078 Legend 1...

Страница 23: ...AR05 039 2 AR05 045 3 AR05 050 4 AR05 060 5 AR05 070 6 AR05 078 Legend 1 AR05 080 2 AR05 090 3 AR05 100 4 AR05 120 5 AR05 140 Legend 1 AR05 039 2 AR05 045 3 AR05 050 4 AR05 060 5 AR05 070 6 AR05 078...

Страница 24: ...peration of two units in master slave mode The control of a master slave assembly is in the entering water and does not require any additional sensors standard con guration It can also be located in t...

Страница 25: ...capacity of the heat pump at 7 C outdoor air temperature This requires only a 400 V 3 ph 50 Hz power supply source as well as a connection to the unit via a communication bus For the required con gura...

Страница 26: ...densables in the system The presence of moisture changes the colour of the indicator paper in the sight glass 14 7 Filter drier This is a one piece brazed lter drier located in the liquid line The rol...

Страница 27: ...complies with JBus protocol Easy connection by communication bus to a building management system AR05 039 160 Bacnet gateway 148C Two directional communications board complies with Bacnet protocol Eas...

Страница 28: ...hly or annually depending on the veri cation type In these conditions the following maintenance operations are recommended Carry out all level 1 operations then Electrical checks At least once a year...

Страница 29: ...Contactor LC1D12B7 KM 1 7 Contactor LC1D18B7 1 7 Contactor LC1D25B7 2 5 Tunnel terminal screw compressor circuit breaker Circuit breaker 25507 QM 3 6 Circuit breaker 25508 Circuit breaker 25509 Tunne...

Страница 30: ...perations 16 7 Water heat exchanger maintenance Check that the insulating foam is intact and securely in place the cooler heaters are operating secure and correctly positioned the water side connectio...

Страница 31: ...nt check Is there any shipping damage If so where Will this damage prevent unit start up Unit is level in its installation Power supply agrees with the unit name plate Electrical circuit wiring has be...

Страница 32: ...nal kW capacity for process cooling Proper loop volume established Proper loop corrosion inhibitor included litres of Proper loop freeze protection included if required litres of Water piping includes...

Страница 33: ...t in the LOCAL ON position Unit starts and operates properly Temperatures and pressures WARNING Once the machine has been operating for a while and the temperatures and pressures have stabilized recor...

Страница 34: ...34 Installation operation and maintenance instructions VMGFE102 VMGFE102...

Отзывы: