8
|
Piping installation
Installer reference guide
93
08CA + EHY EHYHBH/X08A + EHYKOMB33AA
Daikin Altherma hybrid heat pump
4P355634-1G – 2022.09
a
d
j
b
f
e
c
g h i
h
a
Pressure meter
b
Gauge manifold
c
Low pressure valve (Lo)
d
High-pressure valve (Hi)
e
Charging hoses
f
Vacuum pump
g
Service port
h
Valve lids
i
Gas stop valve
j
Liquid stop valve
1
Vacuum the system until the pressure on the manifold indicates −0.1 MPa
(−1 bar).
2
Leave as is for 4-5 minutes and check the pressure:
If the pressure…
Then…
Does not change
There is no moisture in the system.
This procedure is finished.
Increases
There is moisture in the system. Go
to the next step.
3
Vacuum the system for at least 2 hours to a manifold pressure of −0.1 MPa
(−1 bar).
4
After turning the pump OFF, check the pressure for at least 1 hour.
5
If you do NOT reach the target vacuum or CANNOT maintain the vacuum for
1 hour, do the following:
▪
Check for leaks again.
▪
Perform vacuum drying again.
NOTICE
Be sure to open the gas stop valve after piping installation and vacuuming. Running
the system with the valve closed, the compressor may break down.
INFORMATION
After opening the stop valve, it is possible that the pressure in the refrigerant piping
does NOT increase. This might be caused by e.g. the closed state of the expansion
valve in the outdoor unit circuit, but does NOT present any problem for correct
operation of the unit.
8.3.5 To insulate the refrigerant piping
Between outdoor and indoor unit
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.