Specifications:
Voltage- 8 to 24 VDC
OR
+ 5VDC
Current- 100 mA nominal
Range: Up to 10,000 feet for RS-485 versions
May vary due to quality of wiring. Any isolated wire pair will function
with possible degraded performance.
Optimal wiring is shielded twisted pair of 22 ga. or better.
Relay Contact Rating- 2A @ 125 VAC
Digital Input Rating: 0 to + 5 Volts DC standard CMOS logic levels
Digital Output Rating: 25 mA Sink 0.5 mA source (10k pullup resistor)
Aux Digital Output #3 and Aux Digital Output #1 are Open Collector rated at 200mA Sink
Initial Installation
Before installing the units in the field, it is a good idea to connect and apply power to the units on a
bench before installation in the field location. This is especially recommended if there is unfamiliarity
with the Suprex series of products. By initially connecting and powering up the units together, the
operation can be observed on both the Central and Remote. Wiring connections and configuration
can be verified, and any potential problems can be solved much easier than if the units are separated
by several thousand feet.
We recommend that the installation proceed in the following order:
1. Unpackage the units and visually inspect for any shipping damage.
2. Using a power supply or access control panel, apply power to both units using the same power
configuration that will be utilized in the final installation.
3. Connect communication lines RS485 (+) and RS485 ( -) between the Central and Remote.
4. Check LED indicators for normal operation. With the communication lines connected, the Green
Diagnostic led should flash rapidly and the green power LED should be illuminated steady.
5. Check/ Set the dip switch on Central and Remote units for the type of reader data format that
will be used.
6. If a reader and panel are available , connect the reader to the Remote unit and connect the Central
unit to the panel. Using a test badge, verify that the panel can receive badge reads from the reader,
and that the Strike / LED signals are operating in the expected manner.
7. Install the units in their final locations.
See the following pages for details on connection and configuration of the SPX-1200.