26
FIGURE 10.4: TWO-PIPE LIFT SYSTEM
XI Wiring
1)
120 Volt Wiring - Provide the boiler with its own 15A branch circuit with fused disconnect. 120 Volt connections are
made inside the CG450 LWCO as follows (also see Figure 11.0):
•
Connect Hot (“black”) - Wire nut to black pigtail labeled “L1”
•
Connect Neutral (“white”) - Wire nut to white pigtail labeled “L2”
•
Connect Ground (“green” or bare) to green screw on case of CG450
WARNING
• All wiring and grounding must be done in accordance with the authority having jurisdiction
or, in the absence of such requirements, with the
National Electrical Code (ANSI/NFPA 70).
• Disconnect electrical power to the boiler and heating system before servicing. Positively
assure that no voltage is present. Lock electrical boxes to prevent someone from
inadvertently restoring power before the heating system is safe to operate.
• Never defeat or jump out safety devices.
• Protect each boiler circuit with a properly sized over-current protection device.
• Make electrical connections carefully according to the boiler’s wiring diagram and
instructions.
• Wire additional field supplied safety limits, such as low water cutoffs and temperature limit
devices, in series with the 120V circuit used to power the boiler. Do not alter the boiler’s
factory wiring when adding an additional limit device.
Содержание KSB Series
Страница 2: ...2...
Страница 12: ...10 FIGURE 4 1 FIELD INSTALLATION OF FLUE BAFFLES...
Страница 18: ...16 FIGURE 6 4 ALLAIR FROM OUTDOORS USING HORIZONTAL DUCTS INTO BOILER ROOM...
Страница 32: ...30 FIGURE 11 2 INDIRECT WATER HEATER FIELD WIRING...
Страница 43: ...41...