62
3.4.4
Communication Wiring
Instructions for wiring the communications of one or a network of inverters:
1.
Open the inverter wiring box. Refer to Section 3.3.1 for instructions
and torque requirements when replacing cover.
2.
Bring the communication cables into the wiring box through the
provided knockout holes at the bottom, using similar methods to the
AC and DC wiring. Conduit and knockouts must be sealed and water
tight to maintain the NEMA 4X rating.
3.
Connect the RS485 wires to the P7 connector (network P7 and P9)
ensuring correct polarity and using a shielded twisted pair cable.
4.
If the inverter is the last Modbus device in the daisy chain, make sure
the Modbus termination switch S1 is in the ON position enabling
Modbus termination. Do not turn the switch to the ON position in any
other inverters of the daisy chain. If there is only one inverter, the
Modbus termination switch S1 should be set to ON.
5.
The shield of the individual cables must be open (not connected to
ground) on one end
– the other end of the shield must be grounded.
Failure to follow this installation practice will increase lightning surge
damage to the inverter and will void the warranty. See application not
on website:www.chintpowersystems.com/resources.shtml#application
Содержание SCA Series
Страница 2: ......
Страница 35: ...27 ...
Страница 39: ...31 Figure 3 9 Mount the Main Enclosure on the Bracket by Lifting Sling Figure 3 10 Grab Handle Position ...
Страница 91: ...83 ...
Страница 146: ...138 1 5 Figure 8 1 Replacing Cooling Fans 2 3 ...