INSTALLATION GUIDE FOR RA-5200
RA-5200 QI
Copyright - refer to title page
Page 31
ENU Status : 1-0-0
3.2 SITE PLANNING CONSIDERATIONS
Site Considerations
The MOU can be located indoors to facilitate coupling of BTS signals and power supply connections.
The ALC range of received BTS signal is -10~0 dBm. Hence, an appropriate coupler must be used
according to the BTS output power.
The RRU is designed to be waterproof, rainproof, and with snow protection. Temporary protection
should be taken when the equipment enclosure is opened for installation or maintenance in an outdoor
environment. The equipment must not be opened for installation or maintenance in bad weather (e.g.
gale, storm rainfall, extreme temperatures and high humidity)
The site considerations for ROU and RRUs are listed below:
•
The distance between the service antenna of ROU/RRU and coverage area should satisfy line of
sight requirements for maximum coverage area.
•
The maximum fiber length is 20km, with a maximum path loss of 10dB.
•
The system delay of the optical system must be taken into consideration when there are
neighboring BTS sites overlapping in coverage.
Installation Location
Mounting surface shall be capable of supporting the weight of the equipment.
In order to avoid electromagnetic interference, a proper mounting location must be selected to
minimize interference from electromagnetic sources such as large electrical equipment.
Environmental
Humidity has an adverse effect on the reliability of the equipment. It is recommended to install the
equipment in locations having stable temperature and unrestricted air-flow.
The installation location for MOU should be well ventilated. It is recommended that the distance
between the enclosure and the wall (or any other equipments) should be at least 80~100cm. The
equipment has been designed to operate at the temperature range and humidity level as stated in the
product specifications in Reference 0.6.1.
Direct day light to the ROU/RRU should be avoided. If the direct day light temperature exceeds 40
o
C,
a shelter should be provided for it.
Powering
The power supply unit (PSU) provides power to all modules within the equipment. Depending on the
product variant, it is recommended that the PSU operates on a dedicated AC circuit breaker or fused
circuit.
Grounding Requirement
Verify that the equipment has been well grounded. This includes antennas and all cables connected to
the system. Ensure lightning protection for the antennas is properly grounded.